Permit Comments
 

ReviewReview DateStatusComments
Building06/14/2016ApprovedThe Accessibility Compliance Form states full compliance with the Virginia Construction Code. that would require 28 accessible rooms (933 x 3%). Only 21 are provided. If no accessible rooms are being removed, this project can be considered to be not an alteration to a primary function area, and box 2 can be checked. VCC Table 1107.6.1.1.
Electrical 06/13/2016ApprovedPlease clarify the existing panel load, Plans show New rec,, new switches,
Energy  ApprovedThe permit submission indicates that new light switches, switched receptacles, lights and illuminated mirrors are part of the scope of work of the permit. Section C405.2.3 of the 2012 Virginia Energy Conservation Code (VECC) requires that a master control device is installed at the main room entry of each sleeping unit which controls all permanently installed luminaires and switched receptacles of the sleeping unit, including the bathroom. Sheet T2.1 indicates that Leviton Guest Room Solution Lighting Controls will be installed in each ADA room. The notes on sheet T2.1 indicate that the system will control bathroom lighting as well as the hallway lighting but makes no mention of switch controlled receptacles. Sheet A1.0 indicates that s
Energy 06/14/2016ApprovedThe drawings include a Code Summary on sheet T1.0. The Code Summary does not state compliance with the 2012 Virginia Energy Conservation Code (VECC). In the resubmission, revise the Code Summary on sheet T1.0 to list the 2012 Virginia Energy Conservation Code (VECC) under Governing Codes.
Energy 06/14/2016ApprovedThe drawings indicate that new lighting will be installed in corridors, elevator lobbies and seating areas. However, no interior lighting power calculation for these spaces have been submitted. Section C405.5.2 requires that these spaces not exceed a maximum lighting power based on either the "Building Area Method" or the "Space by Space Method.” In the resubmission, include a signed and stamped interior lighting COMcheck on a full size sheet in the drawings that accounts for all lighting, new and existing, in the corridors, elevator lobbies, seating areas and other non-hotel room areas that are part of the permit submission. The COMcheck must compare the design to the 2012 IECC and it may use either the space by space method or the bui
Energy 06/14/2016ApprovedThe permit submission indicates that new light switches, switched receptacles, lights and illuminated mirrors are part of the scope of work of the permit. Section C405.2.3 of the 2012 Virginia Energy Conservation Code (VECC) requires that a master control device is installed at the main room entry of each sleeping unit that controls all permanently installed luminaires and switched receptacles of the sleeping unit, including the bathroom. There does not appear to be a master switch that is capable of controlling all switched receptacles and permanently installed luminaires, such as but not limited to the illuminated mirrors. In the resubmission, show a control device that will satisfy the requirements of section C405.2.3 of the 2012 VECC
Plumbing 06/07/2016ApprovedPg T4.0-#4 Seem to show End Walls Controls in wrong areas. Please advise or correct ANSI 117.1 607.5
Plumbing 06/08/2016ApprovedPlans seem to show tub-to-shower conversion drain area is the same as original with new trench drain in location as old. Please confirm there is no additional piping from the floor below to re-route new drains for tub area. If there is please note and confirm details
Structural 06/15/2016ApprovedNote: Statement of special inspection attached, does not apply to this permit number since no structural work.