DescriptionINTERIOR ALTERATIONS TO EXISTING CVS STORE AND EXTERIOR FACADE RENOVATIONS - APPROVED ADMIN CHANGE - ZADM190408. SPECIAL INSPECTIONS REQUIRED.

ReviewReview DateStatusComments
Building08/22/2019ApprovedSheet 0CS-Cover Sheet: SUBMIT FIRE ALARM SHOP DRAWINGS FOR APPROVAL
Building08/22/2019ApprovedSheet 0CS-Cover Sheet: SEPARATE PLAN AND PERMIT REQUIRED FOR DOORS WITH SPECIAL LOCKING HARDWARE
Building08/22/2019ApprovedSheet 0CS-Cover Sheet: SUBMIT AUTOMATIC SUPPRESSION SHOP DRAWINGS FOR APPROVAL
DES:Water/Sewer Engineering05/04/2020Approvedactive revision for framing changes only
DES:Water/Sewer Engineering09/23/2019ApprovedCTBO INT ALT OF A CVS 17 NEW DFUS CONFIRMED PER COMMENT LETTER FROM BUILDER FIXTURES TO BE COUNTED AS NEW
Electrical05/26/2020No review requiredNo change in resubmission. Approved at earlier submission.
Electrical 08/20/2019ApprovedThere is a reference to the NEC 2005 code, 2011 NEC code and a 2014 NEC, please provide the appropriate code year.
Energy 08/23/2019ApprovedEN-1) comment dated 8-23-19: Sheet A7.1 Window schedule - List on the window and door schedule the Air Infiltration Rate, the U-factor, and the SHGC value of all the NEW fenestration (windows and doors) in the Building thermal Envelope, so compliance with sections C402.4.3 and C402.3.3 can be determined.
Energy 08/23/2019ApprovedEN-7) comment dated 8-23-19: Sheet E1.1 Lighting Plan - clarify what device provides the occupancy / vacancy sensor function in the managers office, the restrooms, the employee room, and the hall. There is no symbol on the legend explaining the Switch sub 'S'. Add symbols to the legend as necessary to clarify that the device providing occupancy/vacancy sensor function.
Energy 08/23/2019ApprovedEN-4) comment dated 8-23-19: Detail 4/A5.1 & on Partitoin Type F on sheet A1.1.- state on the detail the R-value of the insulation, so that I can confirm it meets Table C402.2.
Energy 08/23/2019ApprovedEN-9) comment dated 8-23-19: Sheet M1.2 rooftop schedule - coordinate the total MBH of the RTU's with the size listed on the roof plan M1.3, so that I know which size units I am confirming the efficiency of. Per VECC 109.4.
Energy 09/24/2019ApprovedEN-8) comment dated 8-23-19: Sheet M1.2 rooftop unit schedule - list on the schedule the IEER in addition to the EER that is provided, so that I can confirm the units meet the Table C403.2.3(1).
Energy 10/22/2019ApprovedEN-2) comment dated 10-22-19: Resubmittal may result in additional comments . If you have questi...
Energy 10/22/2019ApprovedEN-5) comment dated 10-22-19: this comment has not been responded to. If the air barrier is to be created by the polyisocyanurate insulation, it will need to be called out as the air barrier, and it will need to be foil faced, per section C402.4.1.2.1, and any penetrations will need to be treated to maintain the air barrier per the manufacturer's requirements. If the air barrier is to be created at the CMU wall, then again, the CMU wall needs to meet the criteria of section C402.4.1.2.1. Call out on the details, which surface/material forms the air barrier. ************************************************ EN-5) comment dated 9-24-19: The response to the previous comment is not accepted. Arlington does not review specificat
Energy 10/22/2019ApprovedEN-3) comment dated 10-22-19: Please number your narrative responses with the identical EN-X number indicated in my comments. This significantly reduces the time required for review of your responses. Per VECC 109.4.
Energy 10/22/2019ApprovedEN-6) comment dated 10-22-19: The previous comment has not been addressed. ******************************************** EN-6) comment dated 9-24-19: The Comcheck analysis is not correctly filled out. You selected the space by space method and associated wattage value for the retail sales area (1.6 w/sf), but applied a much larger square footage than the retail area SF listed on the cover sheet (10K rather than 7K SF) and you did not itemize the other areas of the project nor apply their specific wattage allowances from section C405.5.2. This grossly overstates the wattage allowance allowed for your lighting plan. When using the space by space method, and associated wattage allowance values, you need to apply only the square foota
Environmental Services08/20/2019ApprovedSheet AD-1.1-Demolition Plan: The demo plan doesn't indicate any plumbing fixtures being removed but the P1 note indicates that fixtures will b removed. Please note how many will be removed or if it's a replacement like for like. Contact Aja Moody for any questions 703-228-0777
EPlan Review06/04/2020ApprovedACT REV
EPlan Review11/19/2019Approved--N/A--
Fire Prevention05/26/2020No review requiredSprinkler & fire alarm submission deffered, to be submitted as shop drawings
Mechanical05/26/2020No review requiredNo change in resubmission. Approved at earlier submission.
Plumbing05/26/2020No review requiredNo change in resubmission. Approved at earlier submission.
Plumbing 08/19/2019Approved8-19-19 BFP required before water filter system . 2015 VPC 608.3
Structural 05/12/2020ApprovedStructural Review: REJECTED. Per the new sheet S-2.1 added, please provide the following: 1. Live load for canopy 2. Live load for partition 3. Connection details for the new beams
Structural 08/14/2019ApprovedSpecial Inspections: REJECTED. The statement of special inspection is used by the structural engineer of record (SER) to identify the structural items that require special inspection. This is a legal statement that shall be filled out by the Structural Engineer of Record (SER). All applicable item lines of inspection shall be initialed by both the structural engineer of record (SER) and the special inspection engineer of record (SIER). This statement must contain signatures from the following parties. • Owner • Structural Engineer of Record (SER) • Geotechnical Engineer of Record (GER) • Precast Concrete Engineer of Record (PER) (if applicable) • Special Inspection Engineer of Record (SIER) • Testing Agency Engineer of Record (i
Structural 10/14/2019ApprovedSpecial Inspections: REJECTED. The comment response letter mentions that the statement of special inspections (SSI) packet has been submitted. I looked for it in the new submittal and it was not found. Please submit the SSI packet for review.
Zoning 08/19/2019ApprovedAdministrative change ZADM190408 is still under review at the time of the review of this permit.
Zoning 08/19/2019ApprovedProvide a key plan showing the location of the work to be performed.