Permit Comments
 
Permit #B1903009
Address1550 CRYSTAL DR
TypeCTBO
StatusFINALED
Permit HolderK B R CORPORATION
OwnerCESC SQUARE LLC %JBG SMITH PROPERTIES
Applied Date18/10/2019
Approved Date08/07/2020
Date Issued09/07/2020
DescriptionINTERIOR ALTERATION FOR A NEW CVS PHARMACY STORE SPECIAL INSPECTION REQUIRED (CANOPY) - Active revision

ReviewReview DateStatusComments
Building10/26/2019ApprovedSheet A-7.2-Schedules and Details: Hardware sets HWS-01 through HWS-07 are not provided. Please show on the plans the different hardware sets used.
Building12/02/2019ApprovedSheet 0CS_Cover Sheet: SUBMIT FIRE ALARM SHOP DRAWINGS FOR APPROVAL
Building12/02/2019ApprovedSheet 0CS_Cover Sheet: SEPARATE PLAN AND PERMIT REQUIRED FOR DOORS WITH SPECIAL LOCKING HARDWARE
Building12/02/2019ApprovedSheet 0CS_Cover Sheet: SUBMIT AUTOMATIC SUPPRESSION SHOP DRAWINGS FOR APPROVAL
DES:Engineering11/05/2019ApprovedCTBO INT ALT REMOVE AND REPLACE FIXTURES NO NEW DFUS
DES:Water/Sewer Engineering09/21/2020ApprovedACTIVE REVISION NO DES CHANGES
DES:Water/Sewer Engineering11/04/2020ApprovedACTIVE REVISION NO DES CHANGES
DES:Water/Sewer Engineering12/10/2019ApprovedCTBO INT ALT REMOVE AND REPLACE FIXTURES NO NEW DFUS
Electrical10/08/2020No review required--N/A--
EPlan Review07/08/2020Approved--N/A--
Fire Prevention10/08/2020No review required--N/A--
Mechanical10/08/2020No review required--N/A--
Plumbing10/08/2020No review required--N/A--
Public Health Division10/29/2019ApprovedSheet A-7.3-Floor Finish Plan: Confirm all refrigerators and freezers will be provided with accurate thermometers (± 2° F) and maintained at proper temperature.
Public Health Division10/29/2019ApprovedSheet A-7.3-Floor Finish Plan: Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage. https://health.arlingtonva.us/wp-content/uploads/sites/25/2013/12/PHD-Food-Service-Plan-Review-Application_Fillable.pdf
Public Health Division10/29/2019ApprovedSheet A-7.3-Floor Finish Plan: Confirm there will be a certified food protection manager or certified food handler provided at the pre-opening inspection and at all hours of operation.
Public Health Division10/29/2019ApprovedSheet A-7.3-Floor Finish Plan: Provide the food service equipment layout, with all food service identified in the equipment schedule.
Special Inspection Required10/21/2020RejectedSpecial Inspection required for the added canopy in the active revision.
Special Inspection Required11/18/2020ApprovedSSI - for canopy submitted.
Structural 10/21/2020ApprovedThe Statement of Special Inspection needs to be filled-in & submitted: MUST HAVE: 1). OWNER, SIER, SER, & GC Contact information & Signatures, correct permit #, project address. 2). Initialed inspection boxes (applicable inspections) by SER & SIER 3). Owner, SIER, & SER signatures on inspections sheets. The statement of special inspection is used by the structural engineer of record (SER) to identify the structural items that require special inspection. This is a legal statement that shall be filled out by the Structural Engineer of Record (SER). All applicable item lines of inspection shall be initialed by both the structural engineer of record (SER) and the special inspection engineer of record (SIER). This statement must contain
Structural 11/18/2020ApprovedA-1.2 Plan Sheet: Need Structural Engineer's PE Seal for the structural design notes.
Structural 11/18/2020Approved"A-4.1-Canopy..." drawing - A). This scope of work requires a Structural Engineer's seal. Steel connections, welding, bolting, etc. B).
Zoning 10/18/2020ApprovedZADM200196 submitted 10/7/2020 under review.
Zoning 11/04/2019ApprovedPlease be advised that additional comments may be forthcoming upon submission of revised plans. A comment response letter is required.
Zoning 11/04/2019Approved1. Please provide a location map indicating this space on the site plan.
Zoning 11/04/2019Approved3. Please provide a plan showing that the space will have access to trash collection areas and loading docks.
Zoning 11/04/2019Approved4. Are there any exterior changes to be made? Are you changing out the vestibule doors? Please note facade changes would require an administrative change.
Zoning 11/04/2019Approved5. Please provide an existing floor plan and a demolition plan.
Zoning 12/10/2019ApprovedNo signs are approved with this permit. A separate Certificate of Occupancy will be required for this space.