Review | Review Date | Status | Comments |
Building | 03/16/2021 | Approved | The scope of work presented mentions only demolition and does not mention construction. Please revise scope of work to reflect a summary of the complete proposed.
Code Reference: Virginia Construction Code Sections 109.3
Sheet(s) Reference: A-000 |
Building | 03/16/2021 | Approved | The project shows a change of use and occupancy from a M use group to A2 use group. Please provide a drawing showing the accessible parking and accessible route to the accessible entrance as required by the Virginia Existing Building Code (VEBC) for a complete change of occupancy.
Code Reference: VEBC Section 402.3 |
Building | 03/16/2021 | Approved | It appears that the floorplan used for the life safety/egress plan is different from the architectural floor plan. Please coordinate and use the correct floor plan.
Code Reference: Virginia Construction Code Sections 109.3
Referenced Sheet: LS-001, A-000 |
Building | 03/16/2021 | Approved | It appears that the floorplans for the mechanical and the plumbing disciplines are different from the architectural floor plan. Please coordinate and use the correct floor plan. Check All sheets.
Code Reference: Virginia Construction Code Sections 109.3
Referenced Sheet: P-001 to P-003, M-001 to M-002, E-002 |
Building | 03/16/2021 | Approved | Please clearly show required designated accessible dining surfaces. At least 5 percent, but not less than one, of the dining surfaces for the seating and standing spaces shall be accessible and be distributed throughout the facility and located on a level accessed by an accessible route.
Code Reference: VCC Section 1108.2.3
Referenced Sheet: A-000 |
Building | 03/16/2021 | Approved | Please indicate that the casework, sales/service counters and operable appliances meet the accessibility requirements of 2009 ICC A117.1. |
Building | 03/16/2021 | Approved | The accessibility compliance form provided is not completed correctly. Two boxes are selected on the form submitted. Please check only one box that conveys the level of compliance of the project.
If box 1 is checked, the facility and the alteration are in full compliance with the accessibility requirement.
If box 2 is check, the alteration is limited to equipment upgrades and is not a part of the primary function of the facility.
If box 3 is checked, the alterations done will make the building be in full compliance with the accessibility requirement.
If box 4 is checked, the alterations will be an improvement from the existing accessibility, but the building may not be at the level of full compliance.
For more instructions, pl |
Building | 03/16/2021 | Rejected | Please do not delete any sheets that have already been submitted. For further guidance, please reference the Arlington County’s OnBase/ePlan Review Plan and Document Upload Tutorial:
How to upload documents when submitting revised drawings:
https://www.youtube.com/watch?v=qTzGy8GECpE&feature=youtu.be
If there are any questions or a comment clarification is necessary for this review, please feel free to contact:
Ade Awofisayo (703)228-0542 or aawofisayo@arlingtonva.us |
Building | 03/16/2021 | Rejected | The scope of work presented mentions only demolition and does not mention construction. Please revise scope of work to reflect a summary of the complete proposed.
Code Reference: Virginia Construction Code Sections 109.3
Sheet(s) Reference: A-000
|
Building | 03/16/2021 | Rejected | The project shows a change of use and occupancy from a M use group to A2 use group. Please provide a drawing showing the accessible parking and accessible route to the accessible entrance as required by the Virginia Existing Building Code (VEBC for a complete change of occupancy.
Code Reference: VEBC Section 402.3
|
Building | 03/16/2021 | Rejected | It appears that the floorplan used for the life safety/egress plan is different from the architectural floor plan. Please coordinate and use the correct floor plan.
Code Reference: Virginia Construction Code Sections 109.3
Referenced Sheet: LS-001, A-000
|
Building | 03/16/2021 | Rejected | It appears that the floorplans for the mechanical and the plumbing disciplines are different from the architectural floor plan. Please coordinate and use the correct floor plan. Check All sheets.
Code Reference: Virginia Construction Code Sections 109.3
Referenced Sheet: P-001 to P-003, M-001 to M-002, E-002
|
Building | 03/16/2021 | Rejected | Please clearly show required designated accessible dining surfaces. At least 5 percent, but not less than one, of the dining surfaces for the seating and standing spaces shall be accessible and be distributed throughout the facility and located on a level accessed by an accessible route.
Code Reference: VCC Section 1108.2.3
Referenced Sheet: A-000
|
Building | 03/16/2021 | Rejected | Please indicate that the casework, sales/service counters and operable appliances meet the accessibility requirements of 2009 ICC A117.1. |
Building | 03/16/2021 | Rejected | The accessibility compliance form provided is not completed correctly. Two boxes are selected on the form submitted. Please check only one box that conveys the level of compliance of the project.
If box 1 is checked, the facility and the alteration are in full compliance with the accessibility requirement.
If box 2 is check, the alteration is limited to equipment upgrades and is not a part of the primary function of the facility.
If box 3 is checked, the alterations done will make the building be in full compliance with the accessibility requirement.
If box 4 is checked, the alterations will be an improvement from the existing accessibility, but the building may not be at the level of full compliance.
For more instructions, pl |
Building | 03/16/2021 | Rejected | Door schedule and hardware information is not found on the drawings. Please provide the schedule and door hardware schedule on the drawings to verify compliance with the door and hardware requirements of the Virginia Construction Code.
Code Reference: VCC 2015 Sec 1010
|
Building | 03/16/2021 | Rejected | The scope of work presented mentions only demolition and does not mention construction. Please revise scope of work to reflect a summary of the complete proposed.
Code Reference: Virginia Construction Code Sections 109.3
Sheet(s) Reference: A-000 |
Building | 03/16/2021 | Rejected | The project shows a change of use and occupancy from a M use group to A2 use group. Please provide a drawing showing the accessible parking and accessible route to the accessible entrance as required by the Virginia Existing Building Code (VEBC) for a complete change of occupancy.
Code Reference: VEBC Section 402.3 |
Building | 03/16/2021 | Rejected | It appears that the floorplan used for the life safety/egress plan is different from the architectural floor plan. Please coordinate and use the correct floor plan.
Code Reference: Virginia Construction Code Sections 109.3
Referenced Sheet: LS-001, A-000 |
Building | 03/16/2021 | Rejected | It appears that the floorplans for the mechanical and the plumbing disciplines are different from the architectural floor plan. Please coordinate and use the correct floor plan. Check All sheets.
Code Reference: Virginia Construction Code Sections 109.3
Referenced Sheet: P-001 to P-003, M-001 to M-002, E-002 |
Building | 03/16/2021 | Rejected | Please clearly show required designated accessible dining surfaces. At least 5 percent, but not less than one, of the dining surfaces for the seating and standing spaces shall be accessible and be distributed throughout the facility and located on a level accessed by an accessible route.
Code Reference: VCC Section 1108.2.3
Referenced Sheet: A-000
|
Building | 03/16/2021 | Rejected | Please indicate that the casework, sales/service counters and operable appliances meet the accessibility requirements of 2009 ICC A117.1. |
Building | 03/16/2021 | Rejected | The accessibility compliance form provided is not completed correctly. Two boxes are selected on the form submitted. Please check only one box that conveys the level of compliance of the project.
If box 1 is checked, the facility and the alteration are in full compliance with the accessibility requirement.
If box 2 is check, the alteration is limited to equipment upgrades and is not a part of the primary function of the facility.
If box 3 is checked, the alterations done will make the building be in full compliance with the accessibility requirement.
If box 4 is checked, the alterations will be an improvement from the existing accessibility, but the building may not be at the level of full compliance.
For more instructions, pl |
Building | 04/26/2021 | Approved | Sheet A-001-Architectural Plan: Door maneuvering clearance at push side requires 12 inches (if door has a closer) for compliance with the accessible route.
Reference: 2009 ICC A117.1 Section 402.3
|
Building | 04/26/2021 | Approved | Sheet A-000-Cover Sheet: Change of levels on accessible route shall comply with section 303 for the 2009 ICC A117.1. |
Building | 04/26/2021 | Approved | Sheet A-000-Cover Sheet: Parking spaces and marked aisle shall comply with section 502 for the 2009 ICC A117.1, including floor surfaces, signs for identification, markings and sizes. |
Building | 04/26/2021 | Approved | Sheet A-000-Cover Sheet: Per Section 404.2.3.1 of the 2009 ICC A117.1, Floor surface within the maneuvering clearance of the door shall have a slope not steeper than 1:48 and shall comply with Section 302 of the 2009 ICC A117.1. |
Building | 04/26/2021 | Approved | Sheet A-001-Architectural Plan: Door schedule and hardware information is not found on the drawings. Please provide the schedule and door hardware schedule on the drawings to verify compliance with the door and hardware requirements of the Virginia Construction Code.
Code Reference: VCC 2015 Sec 1010
******************************************************************************************************************04-26-2021: Incomplete Response. I’m sorry I do not understand the door schedule as presented. Door and hardware schedule require that the doors be labeled on the floor plans so that the doors can be identified. There are 6 doors shown on the floor plan (excluding freezer doors), but only 5 shown on the door schedule. Schedu |
Building | 04/26/2021 | Rejected | Sheet A-001-Architectural Plan: Door maneuvering clearance at push side requires 12 inches (if door has a closer) for compliance with the accessible route.
Reference: 2009 ICC A117.1 Section 402.3
|
Building | 04/26/2021 | Rejected | Sheet A-000-Cover Sheet: Change of levels on accessible route shall comply with section 303 for the 2009 ICC A117.1. |
Building | 04/26/2021 | Rejected | Sheet A-000-Cover Sheet: Parking spaces and marked aisle shall comply with section 502 for the 2009 ICC A117.1, including floor surfaces, signs for identification, markings and sizes. |
Building | 04/26/2021 | Rejected | Sheet A-000-Cover Sheet: Per Section 404.2.3.1 of the 2009 ICC A117.1, Floor surface within the maneuvering clearance of the door shall have a slope not steeper than 1:48 and shall comply with Section 302 of the 2009 ICC A117.1. |
Building | 04/26/2021 | Rejected | Sheet A-001-Architectural Plan: Door schedule and hardware information is not found on the drawings. Please provide the schedule and door hardware schedule on the drawings to verify compliance with the door and hardware requirements of the Virginia Construction Code.
Code Reference: VCC 2015 Sec 1010
******************************************************************************************************************04-26-2021: Incomplete Response. I’m sorry I do not understand the door schedule as presented. Door and hardware schedule require that the doors be labeled on the floor plans so that the doors can be identified. There are 6 doors shown on the floor plan (excluding freezer doors), but only 5 shown on the door schedule. Schedu |
Building | 04/27/2021 | Rejected | |
Building | 04/27/2021 | Rejected | Sheet A-001-Architectural Plan: Is this equipment protruding into the egress path? Protruding objects on circulation paths shall comply with the requirements of Sections 1003.3 |
Building | 04/27/2021 | Approved | Please do not delete any sheets that have already been submitted. For further guidance, please reference the Arlington County’s OnBase/ePlan Review Plan and Document Upload Tutorial:
How to upload documents when submitting revised drawings:
https://www.youtube.com/watch?v=qTzGy8GECpE&feature=youtu.be
If there are any questions or a comment clarification is necessary for this review, please feel free to contact:
Ade Awofisayo (703)228-0542 or aawofisayo@arlingtonva.us
******************************************************************************************************************04-26-2021: Additional instruction. Plans must be submitted in landscape format. Please see How to upload documents when submitting revised draw |
Building | 04/27/2021 | Rejected | Please do not delete any sheets that have already been submitted. For further guidance, please reference the Arlington County’s OnBase/ePlan Review Plan and Document Upload Tutorial:
How to upload documents when submitting revised drawings:
https://www.youtube.com/watch?v=qTzGy8GECpE&feature=youtu.be
If there are any questions or a comment clarification is necessary for this review, please feel free to contact:
Ade Awofisayo (703)228-0542 or aawofisayo@arlingtonva.us
******************************************************************************************************************04-26-2021: Additional instruction. Plans must be submitted in landscape format. Please see How to upload documents when submitting revised draw |
Building | 04/27/2021 | Approved | Sheet A-001-Architectural Plan: Is this equipment protruding into the egress path? Protruding objects on circulation paths shall comply with the requirements of Sections 1003.3 |
Building | 04/27/2021 | Rejected | Door schedule and hardware information is not found on the drawings. Please provide the schedule and door hardware schedule on the drawings to verify compliance with the door and hardware requirements of the Virginia Construction Code.
Code Reference: VCC 2015 Sec 1010
******************************************************************************************************************04-26-2021: Incomplete Response. Door and hardware schedule require that the doors be labeled on the floor plans so that the doors can be identified. There are 6 doors shown on the floor plan (excluding freezer doors), but only 5 shown on the door schedule. Schedule is required to show compliance with door egress and accessibility requirements. Field verif |
Building | 04/27/2021 | Approved | Door schedule and hardware information is not found on the drawings. Please provide the schedule and door hardware schedule on the drawings to verify compliance with the door and hardware requirements of the Virginia Construction Code.
Code Reference: VCC 2015 Sec 1010
******************************************************************************************************************04-26-2021: Incomplete Response. Door and hardware schedule require that the doors be labeled on the floor plans so that the doors can be identified. There are 6 doors shown on the floor plan (excluding freezer doors), but only 5 shown on the door schedule. Schedule is required to show compliance with door egress and accessibility requirements. Field verif |
CPHD:Historic Preservation | 04/19/2021 | Approved | --N/A-- |
DES:Water/Sewer Engineering | 06/23/2021 | Approved | COMMERCIAL INT ALT. 6 NEW DFU'S APPROVED |
Energy | 03/19/2021 | Rejected | The electrical drawings indicate new lighting and lighting controls. It is unclear how the new lighting controls satisfy the requirements of section C405.2.1 (Occupant sensor controls) of the 2015 VECC for the "Locked Storage" room. In the resubmission show a design that satisfies the requirements of section C405.2.1 of the 2015 VECC.
|
Energy | 03/19/2021 | Rejected | The electrical drawings indicate new lighting and lighting controls. It is unclear how the new lighting controls satisfy the requirements of section C405.2.2 (Time-switch controls) of the 2015 VECC. All non-emergency lighting must be controlled by either an occupancy sensor or a timeclock. Some areas do not appear to be controlled by either an occupancy sensor or a time-switch control. In the resubmission show a design that satisfies the requirements of section C405.2.1 of the 2015 VECC.
|
Energy | 03/19/2021 | Rejected | The drawings indicate that walk-in coolers/freezers are part of the scope of the permit. The drawings do not call for cooler walls, floors and ceilings with R-values that satisfy the minimum requirements of section C403.2.16 of the 2015 VECC. In the resubmission, revise the drawings to satisfy the minimum R-value requirements of section C403.2.16 of the 2015 VECC for the walk-in cooler/freezers. |
Energy | 03/19/2021 | Rejected | The plumbing drawings indicate that new heated water supply piping is part of the scope of the permit. It is unclear how the new piping will satisfy the requirements of section C404.5 (Efficient heated water supply piping) of the 2015 VECC. Note: for recirculation systems, the circulation loop is the source of heated water.
In the resubmission, revise the heated water supply piping design to satisfy the requirements of this section. |
Energy | 03/19/2021 | Approved | The electrical drawings indicate new lighting and lighting controls. It is unclear how the new lighting controls satisfy the requirements of section C405.2.1 (Occupant sensor controls) of the 2015 VECC for the "Locked Storage" room. In the resubmission show a design that satisfies the requirements of section C405.2.1 of the 2015 VECC. |
Energy | 03/19/2021 | Approved | The electrical drawings indicate new lighting and lighting controls. It is unclear how the new lighting controls satisfy the requirements of section C405.2.2 (Time-switch controls) of the 2015 VECC. All non-emergency lighting must be controlled by either an occupancy sensor or a timeclock. Some areas do not appear to be controlled by either an occupancy sensor or a time-switch control. In the resubmission show a design that satisfies the requirements of section C405.2.1 of the 2015 VECC. |
Energy | 03/19/2021 | Approved | The drawings indicate that walk-in coolers/freezers are part of the scope of the permit. The drawings do not call for cooler walls, floors and ceilings with R-values that satisfy the minimum requirements of section C403.2.16 of the 2015 VECC. In the resubmission, revise the drawings to satisfy the minimum R-value requirements of section C403.2.16 of the 2015 VECC for the walk-in cooler/freezers. |
Energy | 03/19/2021 | Approved | The plumbing drawings indicate that new heated water supply piping is part of the scope of the permit. It is unclear how the new piping will satisfy the requirements of section C404.5 (Efficient heated water supply piping) of the 2015 VECC. Note: for recirculation systems, the circulation loop is the source of heated water.
In the resubmission, revise the heated water supply piping design to satisfy the requirements of this section. |
Energy | 03/19/2021 | Approved | The electrical drawings indicate new lighting and lighting controls. It is unclear how the new lighting controls satisfy the requirements of section C405.2.1 (Occupant sensor controls) of the 2015 VECC for the "Locked Storage" room. In the resubmission show a design that satisfies the requirements of section C405.2.1 of the 2015 VECC. |
Energy | 03/19/2021 | Approved | The electrical drawings indicate new lighting and lighting controls. It is unclear how the new lighting controls satisfy the requirements of section C405.2.2 (Time-switch controls) of the 2015 VECC. All non-emergency lighting must be controlled by either an occupancy sensor or a timeclock. Some areas do not appear to be controlled by either an occupancy sensor or a time-switch control. In the resubmission show a design that satisfies the requirements of section C405.2.1 of the 2015 VECC. |
Energy | 03/19/2021 | Approved | The drawings indicate that walk-in coolers/freezers are part of the scope of the permit. The drawings do not call for cooler walls, floors and ceilings with R-values that satisfy the minimum requirements of section C403.2.16 of the 2015 VECC. In the resubmission, revise the drawings to satisfy the minimum R-value requirements of section C403.2.16 of the 2015 VECC for the walk-in cooler/freezers. |
Energy | 03/19/2021 | Approved | The plumbing drawings indicate that new heated water supply piping is part of the scope of the permit. It is unclear how the new piping will satisfy the requirements of section C404.5 (Efficient heated water supply piping) of the 2015 VECC. Note: for recirculation systems, the circulation loop is the source of heated water.
In the resubmission, revise the heated water supply piping design to satisfy the requirements of this section. |
EPlan Review | 07/20/2021 | Approved | |
Mechanical | 03/15/2021 | Approved | Please provide compliance regarding kitchen hood Type I material per section 507.2.3 IMC2015 (03.15.21) |
Mechanical | 03/15/2021 | Approved | Provide kitchen exhaust calculation per section 403.2 and table 403.3.1.1 (kitchen cooking) IMC2015 (03.15.21) |
Mechanical | 03/15/2021 | Approved | Please provide compliance regarding kitchen hood Type I material per section 507.2.3 IMC2015 (03.15.21) |
Mechanical | 03/15/2021 | Approved | Provide kitchen exhaust calculation per section 403.2 and table 403.3.1.1 (kitchen cooking) IMC2015 (03.15.21) |
Mechanical | 03/15/2021 | Rejected | Please provide compliance regarding kitchen hood Type I material per section 507.2.3 IMC2015 (03.15.21) |
Mechanical | 03/15/2021 | Rejected | Provide kitchen exhaust calculation per section 403.2 and table 403.3.1.1 (kitchen cooking) IMC2015 (03.15.21) |
Plumbing | 03/16/2021 | Rejected | 3-16-21 Please advise, Job description seems to indicate a (White Shell State ) . Plans seem to show new work being performed. |
Plumbing | 03/16/2021 | Approved | 3-16-21 Please advise, Job description seems to indicate a (White Shell State ) . Plans seem to show new work being performed. |
Plumbing | 03/16/2021 | Rejected | 3-16-21 Please advise, Job description seems to indicate a (White Shell State ) . Plans seem to show new work being performed. |
Plumbing | 04/26/2021 | Rejected | A Waste Water Survey Form is required. Please use the link provided. https://arlingtonva.s3.dualstack.us-east-1.amazonaws.com/wp-content/uploads/sites/4/2015/04/Arlington_IU_Survey_2014_140806mod.pdf And forward it to Wilson Dodge the pretreatment coordinator at wrdodge@arlingtonva.us |
Plumbing | 04/26/2021 | Rejected | 4-26-21 Please advise or provide Complete GI Calculations . 2015 VPC 1003.3.4.1 |
Plumbing | 04/26/2021 | Rejected | 4-26-21 Pg P002 Please provide location and details for Tempering devices, If already submitted please advise sheet number and location. 2015 VPC 607.1.2 |
Plumbing | 04/26/2021 | Approved | A Waste Water Survey Form is required. Please use the link provided. https://arlingtonva.s3.dualstack.us-east-1.amazonaws.com/wp-content/uploads/sites/4/2015/04/Arlington_IU_Survey_2014_140806mod.pdf And forward it to Wilson Dodge the pretreatment coordinator at wrdodge@arlingtonva.us |
Plumbing | 04/26/2021 | Approved | 4-26-21 Please advise or provide Complete GI Calculations . 2015 VPC 1003.3.4.1 |
Plumbing | 04/26/2021 | Approved | 4-26-21 Pg P002 Please provide location and details for Tempering devices, If already submitted please advise sheet number and location. 2015 VPC 607.1.2 |
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Provide splash guards for hand sink due to proximity to food prep sinks
|
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Confirm that all exterior doors will be self closing and provided with adequate thresholds and weather stripping to prevent pest entry |
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Confirm that mens and womens restroom shall be provided with self closing hinges or fixtures. |
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Confirm that all exterior doors will be self closing and provided with adequate thresholds and weather stripping to prevent pest entry |
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Confirm that mens and womens restroom shall be provided with self closing hinges or fixtures. |
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Provide splash guards for hand sink due to proximity to food prep sinks
|
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Provide splash guards for hand sink due to proximity to food prep sinks
|
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Confirm that all exterior doors will be self closing and provided with adequate thresholds and weather stripping to prevent pest entry |
Public Health Division | 03/09/2021 | Approved | Sheet KE-001-Kitchen Equipment Plan: Confirm that mens and womens restroom shall be provided with self closing hinges or fixtures. |