Permit Comments
 
Permit #B2102167
Address546 23RD ST S
TypeCTBO
StatusACTIVE
Permit HolderRRF SOLUTIONS LLC
OwnerSOUTH 23RD STREET LLC % SEAPORT PROPERTIES
Applied Date08/09/2021
Approved Date19/05/2022
Date Issued30/05/2022
DescriptionINTERIOR ALTERATION OF TENANT FIT-OUT. PREVIOUS USE WAS A DRY CLEANERS. PROPOSED USE IS FOR A CAFE/LOUNGE.

ReviewReview DateStatusComments
Building02/08/2022ApprovedSheet 546 23RD ST.S: The previous use was a shoe repair/dry cleaners. Please verify the hood exhaust duct meets the requirements for shaft enclosure where it leaves this space and goes up through the building.***** 12/06/21Please include a listed/tested assembly for the grease duct enclosure and a floor plan showing it going through the 2nd floor tenant space.*****02/08/22**** Comment not resolved. Please include notations on the plan set indicating the intended field applied grease duct enclosure complying with VMC 506.3.11.2 and the floor/ceiling assembly penetration will be protected per the included manufacture's instructions which comply with VCC 714.4
Building02/08/2022RejectedSheet 546 23RD ST.S: The previous use was a shoe repair/dry cleaners. Please verify the hood exhaust duct meets the requirements for shaft enclosure where it leaves this space and goes up through the building.***** 12/06/21Please include a listed/tested assembly for the grease duct enclosure and a floor plan showing it going through the 2nd floor tenant space.*****02/08/22**** Comment not resolved. Please include notations on the plan set indicating the intended field applied grease duct enclosure complying with VMC 506.3.11.2 and the floor/ceiling assembly penetration will be protected per the included manufacture's instructions which comply with VCC 714.4
Building09/20/2021RejectedSheet 546 23RD ST.S: Please show accessible route and seating areas per 1109.2.9/2.9.1 VCC.
Building09/20/2021RejectedPlease provide a door and door hardware schedule.
Building09/20/2021RejectedSheet 546 23RD ST.S: Please provide construction details for the booths and the bar.
Building09/20/2021RejectedSheet 546 23RD ST.S - A0: Please provide a key plan showing the building in which this space is located to verify the construction type and any required occupancy separation requirements.
Building09/20/2021ApprovedSheet 546 23RD ST.S: Please show accessible route and seating areas per 1109.2.9/2.9.1 VCC.
Building09/20/2021ApprovedPlease provide a door and door hardware schedule.
Building09/20/2021ApprovedSheet 546 23RD ST.S: Please provide construction details for the booths and the bar.
Building09/20/2021ApprovedSheet 546 23RD ST.S - A0: Please provide a key plan showing the building in which this space is located to verify the construction type and any required occupancy separation requirements.
Building09/20/2021RejectedSheet 546 23RD ST.S: Please show accessible route and seating areas per 1109.2.9/2.9.1 VCC.
Building09/20/2021RejectedPlease provide a door and door hardware schedule.
Building09/20/2021RejectedSheet 546 23RD ST.S: Please provide construction details for the booths and the bar.
Building09/20/2021RejectedSheet 546 23RD ST.S: Please provide ceiling details/reflected ceiling plan
Building09/20/2021RejectedSheet 546 23RD ST.S - A0: Please provide a key plan showing the building in which this space is located to verify the construction type and any required occupancy separation requirements.
Building09/20/2021RejectedSheet 546 23RD ST.S: The proposed new windows may not be allowed based on fire separation distance requirements. Please include a plat plan.
Building09/20/2021RejectedSheet 546 23RD ST.S: The previous use was a shoe repair/dry cleaners. Please verify the hood exhaust duct meets the requirements for shaft enclosure where it leaves this space and goes up through the building.
Building09/20/2021RejectedSheet 546 23RD ST.S: Please show accessible route and seating areas per 1109.2.9/2.9.1 VCC.
Building09/20/2021RejectedPlease provide a door and door hardware schedule.
Building09/20/2021RejectedSheet 546 23RD ST.S: Please provide construction details for the booths and the bar.
Building09/20/2021RejectedSheet 546 23RD ST.S - A0: Please provide a key plan showing the building in which this space is located to verify the construction type and any required occupancy separation requirements.
Building12/06/2021RejectedSheet 546 23RD ST.S: Please provide ceiling details/reflected ceiling plan***** No response found.
Building12/06/2021ApprovedSheet 546 23RD ST.S: Please provide ceiling details/reflected ceiling plan***** No response found.
Building12/06/2021ApprovedSheet AccessibilityComplianceForm2012: 12/06/21 The proposed scope of work is primary function. You will need to select a different option and a compliance path. Minimally you will need to provide upgrades per box# 4.
Building12/06/2021ApprovedYour code analysis does not mention the number of stories. It appears to be a two story structure. You indicate the use to be A-2 for the ground level which is under going this renovation. With no separation between the stories/uses, A-2 un-sprinklered is limited to one story. That being said, for fire separation purposes VCC 303.1.1 allows your space to be classified as a B. Please show this modification to a B use in your code analysis. I also noticed your Accessibility form needs to be corrected .Feel free to reach out with any questions. Chuck Vernon 703-228-3863
Building12/06/2021RejectedSheet 546 23RD ST.S: Please provide ceiling details/reflected ceiling plan***** No response found.
Building12/06/2021RejectedSheet AccessibilityComplianceForm2012: 12/06/21 The proposed scope of work is primary function. You will need to select a different option and a compliance path. Minimally you will need to provide upgrades per box# 4.
Building12/06/2021RejectedYour code analysis does not mention the number of stories. It appears to be a two story structure. You indicate the use to be A-2 for the ground level which is under going this renovation. With no separation between the stories/uses, A-2 un-sprinklered is limited to one story. That being said, for fire separation purposes VCC 303.1.1 allows your space to be classified as a B. Please show this modification to a B use in your code analysis. I also noticed your Accessibility form needs to be corrected .Feel free to reach out with any questions. Chuck Vernon 703-228-3863
Building12/06/2021RejectedSheet 546 23RD ST.S: The previous use was a shoe repair/dry cleaners. Please verify the hood exhaust duct meets the requirements for shaft enclosure where it leaves this space and goes up through the building.***** 12/06/21Please include a listed/tested assembly for the grease duct enclosure and a floor plan showing it going through the 2nd floor tenant space.
Building12/06/2021RejectedSheet AccessibilityComplianceForm2012: 12/06/21 The proposed scope of work is primary function. You will need to select a different option and a compliance path. Minimally you will need to provide upgrades per box# 4.
Building12/06/2021RejectedYour code analysis does not mention the number of stories. It appears to be a two story structure. You indicate the use to be A-2 for the ground level which is under going this renovation. With no separation between the stories/uses, A-2 un-sprinklered is limited to one story. That being said, for fire separation purposes VCC 303.1.1 allows your space to be classified as a B. Please show this modification to a B use in your code analysis. I also noticed your Accessibility form needs to be corrected .Feel free to reach out with any questions. Chuck Vernon 703-228-3863
Building12/17/2021RejectedSheet 546 23RD ST.S: The proposed new windows may not be allowed based on fire separation distance requirements. Please include a plat plan. *****12/02/21 Please remove the windows from all plan sheets. The windows are still shown in the background on MEP plan sheets.
Building12/17/2021ApprovedSheet 546 23RD ST.S: The proposed new windows may not be allowed based on fire separation distance requirements. Please include a plat plan. *****12/02/21 Please remove the windows from all plan sheets. The windows are still shown in the background on MEP plan sheets.
Building12/17/2021RejectedSheet 546 23RD ST.S: The proposed new windows may not be allowed based on fire separation distance requirements. Please include a plat plan. *****12/02/21 Please remove the windows from all plan sheets. The windows are still shown in the background on MEP plan sheets.
DES:Water/Sewer Engineering05/19/2022ApprovedCOMMERCIAL INT ALT INTO CAFE. 12 NEW DFU'S. APPROVED
Electrical09/23/2021RejectedProvide an 'updated' electrical panel board directory for the 'existing' 200 ampere panel board. Section 109.3 of the Virginia Construction Code. Refer to sheet E1.
Electrical09/23/2021RejectedProvide in 'updated' electrical load summary for the 'existing' 200 ampere electrical panel board shown on sheet E1. NOTE: electrical load summary 'must' include existing and new electrical loads. NEC Article 220.87. Section 109.3 of the Virginia Construction Code.
Electrical09/23/2021RejectedComplete the Electrical Energy Certification Form and resubmit with the drawings. This form is required for all new luminaire's and/or controls used on this project. Forms can be down loaded at building.arlingtonva.us. Comcheck is also accepted. Refer to 'Lighting Floor Plan' shown on sheet E1.
Electrical09/23/2021RejectedProvide a 'Lighting Fixture Schedule' for any 'new' luminaire's to be installed. If any. Clarify. Refer to sheet E1
Electrical09/23/2021RejectedThere appears to be an 'existing' electrical panel board located in an 'existing' restroom, above the sink. Refer to sheets A3 and E1. Please clarify.
Electrical09/23/2021RejectedBased on the lack of information provided, the above comments may not constitute a complete list of requested information. Additional design information is required for the county to review for code compliance. Section 109.3 of the Virginia Construction Code.
Electrical09/23/2021ApprovedProvide an 'updated' electrical panel board directory for the 'existing' 200 ampere panel board. Section 109.3 of the Virginia Construction Code. Refer to sheet E1.
Electrical09/23/2021ApprovedProvide in 'updated' electrical load summary for the 'existing' 200 ampere electrical panel board shown on sheet E1. NOTE: electrical load summary 'must' include existing and new electrical loads. NEC Article 220.87. Section 109.3 of the Virginia Construction Code.
Electrical09/23/2021ApprovedComplete the Electrical Energy Certification Form and resubmit with the drawings. This form is required for all new luminaire's and/or controls used on this project. Forms can be down loaded at building.arlingtonva.us. Comcheck is also accepted. Refer to 'Lighting Floor Plan' shown on sheet E1.
Electrical09/23/2021ApprovedProvide a 'Lighting Fixture Schedule' for any 'new' luminaire's to be installed. If any. Clarify. Refer to sheet E1
Electrical09/23/2021ApprovedThere appears to be an 'existing' electrical panel board located in an 'existing' restroom, above the sink. Refer to sheets A3 and E1. Please clarify.
Electrical09/23/2021ApprovedBased on the lack of information provided, the above comments may not constitute a complete list of requested information. Additional design information is required for the county to review for code compliance. Section 109.3 of the Virginia Construction Code.
Electrical09/23/2021RejectedProvide an 'updated' electrical panel board directory for the 'existing' 200 ampere panel board. Section 109.3 of the Virginia Construction Code. Refer to sheet E1.
Electrical09/23/2021RejectedProvide in 'updated' electrical load summary for the 'existing' 200 ampere electrical panel board shown on sheet E1. NOTE: electrical load summary 'must' include existing and new electrical loads. NEC Article 220.87. Section 109.3 of the Virginia Construction Code.
Electrical09/23/2021RejectedComplete the Electrical Energy Certification Form and resubmit with the drawings. This form is required for all new luminaire's and/or controls used on this project. Forms can be down loaded at building.arlingtonva.us. Comcheck is also accepted. Refer to 'Lighting Floor Plan' shown on sheet E1.
Electrical09/23/2021RejectedProvide a 'Lighting Fixture Schedule' for any 'new' luminaire's to be installed. If any. Clarify. Refer to sheet E1
Electrical09/23/2021RejectedThere appears to be an 'existing' electrical panel board located in an 'existing' restroom, above the sink. Refer to sheets A3 and E1. Please clarify.
Electrical09/23/2021RejectedBased on the lack of information provided, the above comments may not constitute a complete list of requested information. Additional design information is required for the county to review for code compliance. Section 109.3 of the Virginia Construction Code.
Electrical09/23/2021ApprovedProvide an 'updated' electrical panel board directory for the 'existing' 200 ampere panel board. Section 109.3 of the Virginia Construction Code. Refer to sheet E1.
Electrical09/23/2021ApprovedProvide in 'updated' electrical load summary for the 'existing' 200 ampere electrical panel board shown on sheet E1. NOTE: electrical load summary 'must' include existing and new electrical loads. NEC Article 220.87. Section 109.3 of the Virginia Construction Code.
Electrical09/23/2021ApprovedComplete the Electrical Energy Certification Form and resubmit with the drawings. This form is required for all new luminaire's and/or controls used on this project. Forms can be down loaded at building.arlingtonva.us. Comcheck is also accepted. Refer to 'Lighting Floor Plan' shown on sheet E1.
Electrical09/23/2021ApprovedProvide a 'Lighting Fixture Schedule' for any 'new' luminaire's to be installed. If any. Clarify. Refer to sheet E1
Electrical09/23/2021ApprovedThere appears to be an 'existing' electrical panel board located in an 'existing' restroom, above the sink. Refer to sheets A3 and E1. Please clarify.
Electrical09/23/2021ApprovedBased on the lack of information provided, the above comments may not constitute a complete list of requested information. Additional design information is required for the county to review for code compliance. Section 109.3 of the Virginia Construction Code.
Electrical12/17/2021ApprovedIn this 2nd review cycle dated (12-6-2021), previous comment #5 has not been addressed. There appears to be no 'required' minimum working clearance in front of the existing panel board. NEC Table 110.26 (A)(1) and 90.4. Clarify. Section 109.3 of the Virginia Construction Code.
Electrical12/17/2021ApprovedBased on the lack of information provided, with respect to previous comment #5, additional comments may be forthcoming.
Electrical12/17/2021RejectedIn this 2nd review cycle dated (12-6-2021), previous comment #5 has not been addressed. There appears to be no 'required' minimum working clearance in front of the existing panel board. NEC Table 110.26 (A)(1) and 90.4. Clarify. Section 109.3 of the Virginia Construction Code.
Electrical12/17/2021RejectedBased on the lack of information provided, with respect to previous comment #5, additional comments may be forthcoming.
Electrical12/17/2021ApprovedIn this 2nd review cycle dated (12-6-2021), previous comment #5 has not been addressed. There appears to be no 'required' minimum working clearance in front of the existing panel board. NEC Table 110.26 (A)(1) and 90.4. Clarify. Section 109.3 of the Virginia Construction Code.
Electrical12/17/2021ApprovedBased on the lack of information provided, with respect to previous comment #5, additional comments may be forthcoming.
EPlan Review05/19/2022ApprovedApproved
Mechanical09/21/2021RejectedPlease provide Type I hood exhaust for medium duty equipment per section 507.2 VMC2018 or provide more information for compliance regarding the existing hood. further comments maybe forthcoming upon resubmission.
Mechanical09/21/2021RejectedProvide bathroom exhaust and termination per section 501.3.1 VMC2018 item #3
Mechanical09/21/2021RejectedPlease illustrate make up air for kitchen area per section 508.1 VMC2018
Mechanical12/10/2021ApprovedPlease provide Type I hood exhaust for medium duty equipment per section 507.2 VMC2018 or provide more information for compliance regarding the existing hood. Field Verify for compliance further comments maybe forthcoming upon resubmission.
Mechanical12/10/2021ApprovedProvide bathroom exhaust and termination per section 501.3.1 VMC2018 item #3 Field Verify for compliance
Mechanical12/10/2021ApprovedPlease illustrate make up air for kitchen area per section 508.1 VMC2018 Field Verify for compliance.
Mechanical12/10/2021ApprovedPlease provide Type I hood exhaust for medium duty equipment per section 507.2 VMC2018 or provide more information for compliance regarding the existing hood. Field Verify for compliance further comments maybe forthcoming upon resubmission.
Mechanical12/10/2021ApprovedProvide bathroom exhaust and termination per section 501.3.1 VMC2018 item #3 Field Verify for compliance
Mechanical12/10/2021ApprovedPlease illustrate make up air for kitchen area per section 508.1 VMC2018 Field Verify for compliance.
Mechanical12/10/2021ApprovedPlease provide Type I hood exhaust for medium duty equipment per section 507.2 VMC2018 or provide more information for compliance regarding the existing hood. Field Verify for compliance further comments maybe forthcoming upon resubmission.
Mechanical12/10/2021ApprovedProvide bathroom exhaust and termination per section 501.3.1 VMC2018 item #3 Field Verify for compliance
Mechanical12/10/2021ApprovedPlease illustrate make up air for kitchen area per section 508.1 VMC2018 Field Verify for compliance.
Plumbing02/04/2022Approved2-4-22 3rd Cycle of review, Comments have not been addressed. Multi issues . Please contact me if you have any questions . James Hemphill 703 819-7512
Plumbing02/04/2022Rejected2-4-22 3rd Cycle of review, Comments have not been addressed. Multi issues . Please contact me if you have any questions . James Hemphill 703 819-7512
Plumbing09/21/2021Approved9-21-21 Additional comments may follow
Plumbing09/21/2021ApprovedA Waste Water Survey Form is required. Please use the link provided. https://arlingtonva.s3.dualstack.us-east-1.amazonaws.com/wp-content/uploads/sites/4/2015/04/Arlington_IU_Survey_2014_140806mod.pdf And forward it to Wilson Dodge the pretreatment coordinator at wrdodge@arlingtonva.us
Plumbing09/21/2021RejectedA Waste Water Survey Form is required. Please use the link provided. https://arlingtonva.s3.dualstack.us-east-1.amazonaws.com/wp-content/uploads/sites/4/2015/04/Arlington_IU_Survey_2014_140806mod.pdf And forward it to Wilson Dodge the pretreatment coordinator at wrdodge@arlingtonva.us
Plumbing09/21/2021Rejected9-21-21 Please provide complete GI calculations and details for Gi . 2015 VPC 1003.3.4.1
Plumbing09/21/2021RejectedA Waste Water Survey Form is required. Please use the link provided. https://arlingtonva.s3.dualstack.us-east-1.amazonaws.com/wp-content/uploads/sites/4/2015/04/Arlington_IU_Survey_2014_140806mod.pdf And forward it to Wilson Dodge the pretreatment coordinator at wrdodge@arlingtonva.us
Plumbing09/21/2021Rejected9-21-21 Please provide required Hand Sink.
Plumbing09/21/2021Rejected9-21-21 Please revise Santi riser to include proper venting, Gi connections , 3 compartment sink connections.
Plumbing09/21/2021Rejected9-21-21 Additional comments may follow
Plumbing09/21/2021RejectedA Waste Water Survey Form is required. Please use the link provided. https://arlingtonva.s3.dualstack.us-east-1.amazonaws.com/wp-content/uploads/sites/4/2015/04/Arlington_IU_Survey_2014_140806mod.pdf And forward it to Wilson Dodge the pretreatment coordinator at wrdodge@arlingtonva.us
Plumbing09/21/2021Rejected9-21-21 Additional comments may follow
Plumbing09/21/2021Rejected9-21-21 Additional comments may follow
Plumbing12/15/2021Rejected12-15-21 Pg P0 seems to indicate gas piping. please advise or provide Gas riser diagram. 2015 VFGC 402
Plumbing12/15/2021Rejected12-15-21 Pg P0 Please provide Water Heater detail.
Plumbing12/15/2021Rejected9-21-21 Please provide complete GI calculations and details for Gi . 2015 VPC 1003.3.4.1 12-15-21 Please provide response to comment.
Plumbing12/15/2021Rejected12-15-21 Pg P0 seems to indicate gas piping. please advise or provide Gas riser diagram. 2015 VFGC 402
Plumbing12/15/2021Rejected12-15-21 Pg P0 Please provide Water Heater detail.
Plumbing12/15/2021Rejected9-21-21 Please provide required Hand Sink. 12-15-21 Please provide response to comment.
Plumbing12/15/2021Rejected9-21-21 Please revise Santi riser to include proper venting, Gi connections , 3 compartment sink connections. 12-15-21 Please provide response to comment.
Plumbing12/15/2021Rejected9-21-21 Please provide complete GI calculations and details for Gi . 2015 VPC 1003.3.4.1 12-15-21 Please provide response to comment.
Plumbing12/15/2021Rejected9-21-21 Please provide required Hand Sink. 12-15-21 Please provide response to comment.
Plumbing12/15/2021Rejected9-21-21 Please revise Santi riser to include proper venting, Gi connections , 3 compartment sink connections. 12-15-21 Please provide response to comment.
Plumbing12/15/2021Approved9-21-21 Please provide complete GI calculations and details for Gi . 2015 VPC 1003.3.4.1 12-15-21 Please provide response to comment.
Plumbing12/15/2021Approved9-21-21 Please provide required Hand Sink. 12-15-21 Please provide response to comment.
Plumbing12/15/2021Approved9-21-21 Please revise Santi riser to include proper venting, Gi connections , 3 compartment sink connections. 12-15-21 Please provide response to comment.
Plumbing12/15/2021Approved12-15-21 Pg P0 seems to indicate gas piping. please advise or provide Gas riser diagram. 2015 VFGC 402
Plumbing12/15/2021Approved12-15-21 Pg P0 Please provide Water Heater detail.
Plumbing12/15/2021Rejected9-21-21 Please provide required Hand Sink. 12-15-21 Please provide response to comment.
Public Health Division09/14/2021ApprovedSheet 546 23RD ST.S: Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf
Public Health Division09/14/2021ApprovedSheet 546 23RD ST.S: Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked.
Public Health Division09/14/2021ApprovedSheet 546 23RD ST.S: Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage. https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
Public Health Division09/14/2021RejectedSheet 546 23RD ST.S: Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf
Public Health Division09/14/2021RejectedSheet 546 23RD ST.S: Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked.
Public Health Division09/14/2021RejectedSheet 546 23RD ST.S: Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage. https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
Public Health Division09/14/2021RejectedSheet 546 23RD ST.S: Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf
Public Health Division09/14/2021RejectedSheet 546 23RD ST.S: Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked.
Public Health Division09/14/2021RejectedSheet 546 23RD ST.S: Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage. https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
Public Health Division09/14/2021ApprovedSheet 546 23RD ST.S: Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf
Public Health Division09/14/2021ApprovedSheet 546 23RD ST.S: Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked.
Public Health Division09/14/2021ApprovedSheet 546 23RD ST.S: Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage. https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
Public Health Division12/06/2021ApprovedSheet 546 23RD ST.S: Complete and upload the Food Establishment License Application: https://www.arlingtonva.us/files/sharedassets/public/health/documents/2022-food-establishment-application_fillable_2021.10.15.pdf
Public Health Division12/06/2021RejectedSheet 546 23RD ST.S: Complete and upload the Food Establishment License Application: https://www.arlingtonva.us/files/sharedassets/public/health/documents/2022-food-establishment-application_fillable_2021.10.15.pdf
Public Health Division12/06/2021ApprovedSheet 546 23RD ST.S: Complete and upload the Food Establishment License Application: https://www.arlingtonva.us/files/sharedassets/public/health/documents/2022-food-establishment-application_fillable_2021.10.15.pdf