Review | Review Date | Status | Comments |
Building | 02/09/2022 | Approved | Sheet A104-1 SITE AND INTERIOR PLANS: What is slope of existing ramp? If over 1:20 handrails are required on both sides. (Plan shows just one side). Edge protection required |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: Elevation of front door does not match what is shown on the door/ hardware schedule. Refer to A117.1, Section 404.2.9 - 10" h bottom rail required on push side of door |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: see cloud on plan. 44" clear path required to 2nd required exit. In addition, refer to A117.1, Section 404.2.3 - Maneuvering clearance is not met at doors in this reduced width corridor |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: New exterior door is added to the back of establishment. Provide detail with header information to show framing for new exterior opening |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: Refer to Section 2406.4.2 - Safety glazing is required at windows adjacent to new door |
Building | 02/09/2022 | Approved | Sheet A014 ADA PLAN: include accessible parking and exterior existing ramp on plan to show the accessible route. Include the accessible parking dimensions and access aisle dimension. Accessible parking to comply with Section 1106.8 for identification requirements and A117.1, section 502 for sizing |
Building | 02/09/2022 | Approved | Sheet A104-1 SITE AND INTERIOR PLANS: What is slope of existing ramp? If over 1:20 handrails are required on both sides. (Plan shows just one side). Edge protection required |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: Elevation of front door does not match what is shown on the door/ hardware schedule. Refer to A117.1, Section 404.2.9 - 10" h bottom rail required on push side of door |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: see cloud on plan. 44" clear path required to 2nd required exit. In addition, refer to A117.1, Section 404.2.3 - Maneuvering clearance is not met at doors in this reduced width corridor |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: New exterior door is added to the back of establishment. Provide detail with header information to show framing for new exterior opening |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: Refer to Section 2406.4.2 - Safety glazing is required at windows adjacent to new door |
Building | 02/09/2022 | Approved | Sheet A014 ADA PLAN: include accessible parking and exterior existing ramp on plan to show the accessible route. Include the accessible parking dimensions and access aisle dimension. Accessible parking to comply with Section 1106.8 for identification requirements and A117.1, section 502 for sizing |
Building | 02/09/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: Refer to Section 603 and Section 803.13. Building construction type shown as 2B construction. Non combustible or FRT required for underlayment/sheathing on partitions. |
Building | 02/09/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: Refer to Section 1010.1.1. Min 32" clear door opening required measured door face to jamb. Both restroom doors (type 1)scheduled as 30" wide. In addition, BOH door (type 2) is a double door with 2 - 1'-6" leaves. One leaf in a pair is required to meet the 32" clearance requirement. |
Building | 02/09/2022 | Rejected | Sheet A107 FRAMING PLAN: see cloud on plan. 44" clear path required to 2nd required exit. In addition, refer to A117.1, Section 404.2.3 - Maneuvering clearance is not met at doors in this reduced width corridor |
Building | 02/09/2022 | Rejected | Sheet A107 FRAMING PLAN: New exterior door is added to the back of establishment. Provide detail with header information to show framing for new exterior opening |
Building | 02/09/2022 | Rejected | Sheet A107 FRAMING PLAN: Refer to Section 2406.4.2 - Safety glazing is required at windows adjacent to new door |
Building | 02/09/2022 | Rejected | Sheet A014 ADA PLAN: include accessible parking and exterior existing ramp on plan to show the accessible route. Include the accessible parking dimensions and access aisle dimension. Accessible parking to comply with Section 1106.8 for identification requirements and A117.1, section 502 for sizing |
Building | 02/09/2022 | Rejected | Sheet A104-1 SITE AND INTERIOR PLANS: Stair to new door is new. Provide framing/ structural information and details to show compliance. Provide dimensions for stair and landing (landing does not appear compliant). Comply with Section 1011. Handrails and guard (if required) to Comply with Sections 1014 and 1015, including handrail extensions |
Building | 02/09/2022 | Rejected | Sheet A104-1 SITE AND INTERIOR PLANS: What is slope of existing ramp? If over 1:20 handrails are required on both sides. (Plan shows just one side). Edge protection required |
Building | 02/09/2022 | Rejected | Sheet A107 FRAMING PLAN: Elevation of front door does not match what is shown on the door/ hardware schedule. Refer to A117.1, Section 404.2.9 - 10" h bottom rail required on push side of door |
Building | 02/09/2022 | Approved | Sheet A104-1 SITE AND INTERIOR PLANS: What is slope of existing ramp? If over 1:20 handrails are required on both sides. (Plan shows just one side). Edge protection required |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: Elevation of front door does not match what is shown on the door/ hardware schedule. Refer to A117.1, Section 404.2.9 - 10" h bottom rail required on push side of door |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: see cloud on plan. 44" clear path required to 2nd required exit. In addition, refer to A117.1, Section 404.2.3 - Maneuvering clearance is not met at doors in this reduced width corridor |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: New exterior door is added to the back of establishment. Provide detail with header information to show framing for new exterior opening |
Building | 02/09/2022 | Approved | Sheet A107 FRAMING PLAN: Refer to Section 2406.4.2 - Safety glazing is required at windows adjacent to new door |
Building | 02/09/2022 | Approved | Sheet A014 ADA PLAN: include accessible parking and exterior existing ramp on plan to show the accessible route. Include the accessible parking dimensions and access aisle dimension. Accessible parking to comply with Section 1106.8 for identification requirements and A117.1, section 502 for sizing |
Building | 02/09/2022 | Rejected | Sheet A107 FRAMING PLAN: see cloud on plan. 44" clear path required to 2nd required exit. In addition, refer to A117.1, Section 404.2.3 - Maneuvering clearance is not met at doors in this reduced width corridor |
Building | 02/09/2022 | Rejected | Sheet A107 FRAMING PLAN: New exterior door is added to the back of establishment. Provide detail with header information to show framing for new exterior opening |
Building | 02/09/2022 | Rejected | Sheet A107 FRAMING PLAN: Refer to Section 2406.4.2 - Safety glazing is required at windows adjacent to new door |
Building | 02/09/2022 | Rejected | Sheet A014 ADA PLAN: include accessible parking and exterior existing ramp on plan to show the accessible route. Include the accessible parking dimensions and access aisle dimension. Accessible parking to comply with Section 1106.8 for identification requirements and A117.1, section 502 for sizing |
Building | 02/09/2022 | Rejected | Sheet A104-1 SITE AND INTERIOR PLANS: What is slope of existing ramp? If over 1:20 handrails are required on both sides. (Plan shows just one side). Edge protection required |
Building | 02/09/2022 | Rejected | Sheet A107 FRAMING PLAN: Elevation of front door does not match what is shown on the door/ hardware schedule. Refer to A117.1, Section 404.2.9 - 10" h bottom rail required on push side of door |
Building | 03/11/2022 | Rejected | Sheet A400 RESTROOM PLAN: Door approach from inside ADA WC is not adequate if door has a closer. I don't see a closer specified on current door hardware., but it is typically added when a door is spec'd with push/ pull hardware. Please coordinate and confirm |
Building | 03/11/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: Door 3 is marked as exit only on plans. No operating hardware is permitted on exterior if this door is required to be exit only |
Building | 03/11/2022 | Rejected | Sheet A003 LIFE SAFETY: Refer to Section 1011.2 - Stair to be min. 44" wide. |
Building | 03/11/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: Refer to Section 603 and Section 803.13. Building construction type shown as 2B construction. Non combustible or FRT required for underlayment/sheathing on partitions.
****************03/11/22 - Narrative states change was made to this sheet, but this sheet has not been updated. Comment remains |
Building | 03/11/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: Refer to Section 1010.1.1. Min 32" clear door opening required measured door face to jamb. Both restroom doors (type 1)scheduled as 30" wide. In addition, BOH door (type 2) is a double door with 2 - 1'-6" leaves. One leaf in a pair is required to meet the 32" clearance requirement.
***************03/11/22 - Narrative states revision change, but no change has been made to this sheet. Comment remains |
Building | 03/11/2022 | Rejected | Sheet A104-1 SITE AND INTERIOR PLANS: Stair to new door is new. Provide framing/ structural information and details to show compliance. Provide dimensions for stair and landing (landing does not appear compliant). Comply with Section 1011. Handrails and guard (if required) to Comply with Sections 1014 and 1015, including handrail extensions
*******************03/11/22 - New structural and architectural information does not give stair geometry including rise and run. This needs to be represented on drawings. While not indicated on plans, the landing appears to be over 30" requiring a guard per Section 1015 is required |
Building | 03/11/2022 | Approved | Sheet A104-1 SITE AND INTERIOR PLANS: Stair to new door is new. Provide framing/ structural information and details to show compliance. Provide dimensions for stair and landing (landing does not appear compliant). Comply with Section 1011. Handrails and guard (if required) to Comply with Sections 1014 and 1015, including handrail extensions
*******************03/11/22 - New structural and architectural information does not give stair geometry including rise and run. This needs to be represented on drawings. While not indicated on plans, the landing appears to be over 30" requiring a guard per Section 1015 is required |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Refer to Section 603 and Section 803.13. Building construction type shown as 2B construction. Non combustible or FRT required for underlayment/sheathing on partitions.
****************03/11/22 - Narrative states change was made to this sheet, but this sheet has not been updated. Comment remains |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Refer to Section 1010.1.1. Min 32" clear door opening required measured door face to jamb. Both restroom doors (type 1)scheduled as 30" wide. In addition, BOH door (type 2) is a double door with 2 - 1'-6" leaves. One leaf in a pair is required to meet the 32" clearance requirement.
***************03/11/22 - Narrative states revision change, but no change has been made to this sheet. Comment remains |
Building | 03/11/2022 | Approved | Sheet A400 RESTROOM PLAN: Door approach from inside ADA WC is not adequate if door has a closer. I don't see a closer specified on current door hardware., but it is typically added when a door is spec'd with push/ pull hardware. Please coordinate and confirm |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Door 3 is marked as exit only on plans. No operating hardware is permitted on exterior if this door is required to be exit only |
Building | 03/11/2022 | Approved | Sheet A003 LIFE SAFETY: Refer to Section 1011.2 - Stair to be min. 44" wide. |
Building | 03/11/2022 | Approved | Sheet A104-1 SITE AND INTERIOR PLANS: Stair to new door is new. Provide framing/ structural information and details to show compliance. Provide dimensions for stair and landing (landing does not appear compliant). Comply with Section 1011. Handrails and guard (if required) to Comply with Sections 1014 and 1015, including handrail extensions
*******************03/11/22 - New structural and architectural information does not give stair geometry including rise and run. This needs to be represented on drawings. While not indicated on plans, the landing appears to be over 30" requiring a guard per Section 1015 is required |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Refer to Section 603 and Section 803.13. Building construction type shown as 2B construction. Non combustible or FRT required for underlayment/sheathing on partitions.
****************03/11/22 - Narrative states change was made to this sheet, but this sheet has not been updated. Comment remains |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Refer to Section 1010.1.1. Min 32" clear door opening required measured door face to jamb. Both restroom doors (type 1)scheduled as 30" wide. In addition, BOH door (type 2) is a double door with 2 - 1'-6" leaves. One leaf in a pair is required to meet the 32" clearance requirement.
***************03/11/22 - Narrative states revision change, but no change has been made to this sheet. Comment remains |
Building | 03/11/2022 | Approved | Sheet A400 RESTROOM PLAN: Door approach from inside ADA WC is not adequate if door has a closer. I don't see a closer specified on current door hardware., but it is typically added when a door is spec'd with push/ pull hardware. Please coordinate and confirm |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Door 3 is marked as exit only on plans. No operating hardware is permitted on exterior if this door is required to be exit only |
Building | 03/11/2022 | Approved | Sheet A003 LIFE SAFETY: Refer to Section 1011.2 - Stair to be min. 44" wide. |
Building | 03/11/2022 | Approved | Sheet A104-1 SITE AND INTERIOR PLANS: Stair to new door is new. Provide framing/ structural information and details to show compliance. Provide dimensions for stair and landing (landing does not appear compliant). Comply with Section 1011. Handrails and guard (if required) to Comply with Sections 1014 and 1015, including handrail extensions
*******************03/11/22 - New structural and architectural information does not give stair geometry including rise and run. This needs to be represented on drawings. While not indicated on plans, the landing appears to be over 30" requiring a guard per Section 1015 is required |
Building | 03/11/2022 | Approved | Sheet A400 RESTROOM PLAN: Door approach from inside ADA WC is not adequate if door has a closer. I don't see a closer specified on current door hardware., but it is typically added when a door is spec'd with push/ pull hardware. Please coordinate and confirm |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Door 3 is marked as exit only on plans. No operating hardware is permitted on exterior if this door is required to be exit only |
Building | 03/11/2022 | Approved | Sheet A003 LIFE SAFETY: Refer to Section 1011.2 - Stair to be min. 44" wide. |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Refer to Section 603 and Section 803.13. Building construction type shown as 2B construction. Non combustible or FRT required for underlayment/sheathing on partitions.
****************03/11/22 - Narrative states change was made to this sheet, but this sheet has not been updated. Comment remains |
Building | 03/11/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: Refer to Section 1010.1.1. Min 32" clear door opening required measured door face to jamb. Both restroom doors (type 1)scheduled as 30" wide. In addition, BOH door (type 2) is a double door with 2 - 1'-6" leaves. One leaf in a pair is required to meet the 32" clearance requirement.
***************03/11/22 - Narrative states revision change, but no change has been made to this sheet. Comment remains |
Building | 04/14/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: DEADBOLTS AT RESTROOM DOORS TO HAVE ELONGATED (ACCESSIBLE) THUMBTURNS |
Building | 04/14/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: REFER TO A117.1, SECTION 404.2.10. VISION PANELS ON DOORS TO BE 43" AFF MAX TO BOTTOM OF PANEL |
Building | 04/14/2022 | Approved | Sheet 00 CERTIFICATE OF OCCUPANCY APPLICATION: CERTIFICATE FOR OCCUPANCY APPLICATION IS NOT APPLIED THROUGH THE BUILDING PERMIT. A SEPARATE SUBMISSION IS REQUIRED |
Building | 04/14/2022 | Approved | Sheet A000 COVER SHEET: SUBMIT FIRE ALARM SHOP DRAWINGS FOR APPROVAL |
Building | 04/14/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: DEADBOLTS AT RESTROOM DOORS TO HAVE ELONGATED (ACCESSIBLE) THUMBTURNS |
Building | 04/14/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: REFER TO A117.1, SECTION 404.2.10. VISION PANELS ON DOORS TO BE 43" AFF MAX TO BOTTOM OF PANEL |
Building | 04/14/2022 | Approved | Sheet 00 CERTIFICATE OF OCCUPANCY APPLICATION: CERTIFICATE FOR OCCUPANCY APPLICATION IS NOT APPLIED THROUGH THE BUILDING PERMIT. A SEPARATE SUBMISSION IS REQUIRED |
Building | 04/14/2022 | Approved | Sheet A000 COVER SHEET: SUBMIT FIRE ALARM SHOP DRAWINGS FOR APPROVAL |
Building | 04/14/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: DEADBOLTS AT RESTROOM DOORS TO HAVE ELONGATED (ACCESSIBLE) THUMBTURNS |
Building | 04/14/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: REFER TO A117.1, SECTION 404.2.10. VISION PANELS ON DOORS TO BE 43" AFF MAX TO BOTTOM OF PANEL |
Building | 04/14/2022 | Approved | Sheet 00 CERTIFICATE OF OCCUPANCY APPLICATION: CERTIFICATE FOR OCCUPANCY APPLICATION IS NOT APPLIED THROUGH THE BUILDING PERMIT. A SEPARATE SUBMISSION IS REQUIRED |
Building | 04/14/2022 | Approved | Sheet A000 COVER SHEET: SUBMIT FIRE ALARM SHOP DRAWINGS FOR APPROVAL |
Building | 05/25/2022 | Approved | Plan review cycle ended and plans returned at submitter's request to add new revision.. |
Building | 05/25/2022 | Approved | Plan review cycle ended and plans returned at submitter's request to add new revision.. |
DES:Water/Sewer Engineering | 05/19/2022 | Approved | COMMERCIAL INT ALT. 9.50 NEW DFU'S. APPROVED |
Energy | 02/16/2022 | Rejected | Sheet A001 ZONING AND BUILDING INFO: EN-1) 02/16/22: NOT USED. |
Energy | 02/16/2022 | Rejected | Sheet A104 FLOOR PLAN: EN-2) 02/16/22 - Label the new door with an identification tag, for purposes of addressing the energy criteria associated with new fenestration. |
Energy | 02/16/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: EN-03) 02/16/22 : New doors and new windows/storefront/curtainwall glazing in the building thermal envelope shall meet the energy code requirements for all three of these metrics: A) the Air Infiltration Rate (whether glazed or opaque), B) the U-factor (whether glazed or opaque) and C) SHGC value (if glazed). Reference Tables C402.1.4, C402.4, C402.5.2. Per Existing Building Code 601.4. State ON THE DRAWINGS the numeric values for your specific fenestration types on the drawings. Citing only the code section numbers will not be sufficient to comply with the code. |
Energy | 02/16/2022 | Rejected | Sheet E101 RCP: EN-4) 02/16/22 COMCHECK – The incorrect space type has been entered into comcheck to determine the allowed wattage. You have opted to use the space by space method from Table C405.3.2(2). Each space’s function must be assigned the most closely matched category available. Café seating and dining would be Dining Area, and would be either lounge/bar or fast food, but NOT retail. The Bathroom would fall under Restroom NOT retail, the BOH needs to be separated in to Storage (former vault) and Food Prep Area, but NOT retail. Revise and resubmit. |
Energy | 02/16/2022 | Rejected | Sheet E101 RCP: EN-5) 02/16/22 Lighting Controls – Provide the required occupancy sensors per C405.2.1, in the storage room. Revise and resubmit. |
Energy | 02/16/2022 | Rejected | Sheet E101 RCP: EN-6) 02/16/22 Lighting Controls – Provide the required manual controls light reduction for the areas that are NOT in a daylighting zone and that are NOT controlled by an occupancy sensor, per C405.2.2.1 and C405.2.2.2. Revise and resubmit. |
Energy | 02/16/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: EN-07) 02/16/22 - On the rooftop unit schedule, in addition to the EER listed for the new unit, list the IEER, to comply with Table C403.3.2(1). |
Energy | 02/16/2022 | Rejected | Sheet P600 PLUMBING DETAILS: EN-08) 02/16/22 - Provide ON THE DRAWINGS a schedule of the gas tankless water heater. Include its size, andits minimum required efficiency from Tab;e C404.2. |
Energy | 02/16/2022 | Rejected | EN-09) 02/16/22: Resubmission may result in additional comments. Please number your narrative responses with the identical EN-X number indicated in my comments. This significantly reduces the time required for review of your responses. Per VECC 109.4. If you have questions regarding this energy code review, you can contact me via email at lbaskerville@arlingtonva.us, or call on my mobile number 703-244-0479. The Virginia Energy Conservation Code can be found free online at https://codes.iccsafe.org/content/VECC2018P1 |
Energy | 03/22/2022 | Approved | Sheet P600 PLUMBING DETAILS: EN-08) 02/16/22 - Provide ON THE DRAWINGS a schedule of the gas tankless water heater. Include its size, and its minimum required efficiency from Tab;e C404.2. |
Energy | 03/22/2022 | Approved | Sheet A001 ZONING AND BUILDING INFO: EN-1) EN-1) 03/22/22 – Current code year cycle is 2018, with the option to use 2015 until June 30, 2022. Your code summary indicates 2012. For Energy Code compliance purposes, you need to state in your code summary section whether you are following VECC or ASHRAE 90.1, and which year. Revise and resubmit. Per VCC section 101.2.*******************************02/16/22: NOT USED. |
Energy | 03/22/2022 | Approved | Sheet A104 FLOOR PLAN: EN-2) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 - Label the new door with an identification tag, for purposes of addressing the energy criteria associated with new fenestration. |
Energy | 03/22/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: EN-03) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 : New doors and new windows/storefront/curtainwall glazing in the building thermal envelope shall meet the energy code requirements for all three of these metrics: A) the Air Infiltration Rate (whether glazed or opaque), B) the U-factor (whether glazed or opaque) and C) SHGC value (if glazed). Reference Tables C402.1.4, C402.4, C402.5.2. Per Existing Building Code 601.4. State ON THE DRAWINGS the numeric values for your specific fenestration types on the drawings. Citing only the code section numbe |
Energy | 03/22/2022 | Approved | Sheet E101 RCP: EN-4) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 COMCHECK – The incorrect space type has been entered into comcheck to determine the allowed wattage. You have opted to use the space by space method from Table C405.3.2(2). Each space’s function must be assigned the most closely matched category available. Café seating and dining would be Dining Area, and would be either lounge/bar or fast food, but NOT retail. The Bathroom would fall under Restroom NOT retail, the BOH needs to be separated in to Storage (former vault) and Food Prep Area, but NOT retail. Revise and |
Energy | 03/22/2022 | Approved | Sheet E101 RCP: EN-5) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 Lighting Controls – Provide the required occupancy sensors per C405.2.1, in the storage room. Revise and resubmit. |
Energy | 03/22/2022 | Approved | Sheet E101 RCP: EN-6) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 Lighting Controls – Provide the required manual controls light reduction for the areas that are NOT in a daylighting zone and that are NOT controlled by an occupancy sensor, per C405.2.2.1 and C405.2.2.2. Revise and resubmit. |
Energy | 03/22/2022 | Approved | Sheet A001 ZONING AND BUILDING INFO: EN-1) EN-1) 03/22/22 – Current code year cycle is 2018, with the option to use 2015 until June 30, 2022. Your code summary indicates 2012. For Energy Code compliance purposes, you need to state in your code summary section whether you are following VECC or ASHRAE 90.1, and which year. Revise and resubmit. Per VCC section 101.2.*******************************02/16/22: NOT USED. |
Energy | 03/22/2022 | Approved | Sheet A104 FLOOR PLAN: EN-2) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 - Label the new door with an identification tag, for purposes of addressing the energy criteria associated with new fenestration. |
Energy | 03/22/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: EN-03) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 : New doors and new windows/storefront/curtainwall glazing in the building thermal envelope shall meet the energy code requirements for all three of these metrics: A) the Air Infiltration Rate (whether glazed or opaque), B) the U-factor (whether glazed or opaque) and C) SHGC value (if glazed). Reference Tables C402.1.4, C402.4, C402.5.2. Per Existing Building Code 601.4. State ON THE DRAWINGS the numeric values for your specific fenestration types on the drawings. Citing only the code section numbe |
Energy | 03/22/2022 | Approved | Sheet E101 RCP: EN-4) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 COMCHECK – The incorrect space type has been entered into comcheck to determine the allowed wattage. You have opted to use the space by space method from Table C405.3.2(2). Each space’s function must be assigned the most closely matched category available. Café seating and dining would be Dining Area, and would be either lounge/bar or fast food, but NOT retail. The Bathroom would fall under Restroom NOT retail, the BOH needs to be separated in to Storage (former vault) and Food Prep Area, but NOT retail. Revise and |
Energy | 03/22/2022 | Approved | Sheet E101 RCP: EN-5) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 Lighting Controls – Provide the required occupancy sensors per C405.2.1, in the storage room. Revise and resubmit. |
Energy | 03/22/2022 | Approved | Sheet E101 RCP: EN-6) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 Lighting Controls – Provide the required manual controls light reduction for the areas that are NOT in a daylighting zone and that are NOT controlled by an occupancy sensor, per C405.2.2.1 and C405.2.2.2. Revise and resubmit. |
Energy | 03/22/2022 | Rejected | Sheet A001 ZONING AND BUILDING INFO: EN-1) EN-1) 03/22/22 – Current code year cycle is 2018, with the option to use 2015 until June 30, 2022. Your code summary indicates 2012. For Energy Code compliance purposes, you need to state in your code summary section whether you are following VECC or ASHRAE 90.1, and which year. Revise and resubmit. Per VCC section 101.2.*******************************02/16/22: NOT USED. |
Energy | 03/22/2022 | Rejected | Sheet A104 FLOOR PLAN: EN-2) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 - Label the new door with an identification tag, for purposes of addressing the energy criteria associated with new fenestration. |
Energy | 03/22/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: EN-03) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 : New doors and new windows/storefront/curtainwall glazing in the building thermal envelope shall meet the energy code requirements for all three of these metrics: A) the Air Infiltration Rate (whether glazed or opaque), B) the U-factor (whether glazed or opaque) and C) SHGC value (if glazed). Reference Tables C402.1.4, C402.4, C402.5.2. Per Existing Building Code 601.4. State ON THE DRAWINGS the numeric values for your specific fenestration types on the drawings. Citing only the code section numbe |
Energy | 03/22/2022 | Rejected | Sheet E101 RCP: EN-4) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 COMCHECK – The incorrect space type has been entered into comcheck to determine the allowed wattage. You have opted to use the space by space method from Table C405.3.2(2). Each space’s function must be assigned the most closely matched category available. Café seating and dining would be Dining Area, and would be either lounge/bar or fast food, but NOT retail. The Bathroom would fall under Restroom NOT retail, the BOH needs to be separated in to Storage (former vault) and Food Prep Area, but NOT retail. Revise and |
Energy | 03/22/2022 | Rejected | Sheet E101 RCP: EN-5) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 Lighting Controls – Provide the required occupancy sensors per C405.2.1, in the storage room. Revise and resubmit. |
Energy | 03/22/2022 | Rejected | Sheet E101 RCP: EN-6) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 Lighting Controls – Provide the required manual controls light reduction for the areas that are NOT in a daylighting zone and that are NOT controlled by an occupancy sensor, per C405.2.2.1 and C405.2.2.2. Revise and resubmit. |
Energy | 03/22/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: EN-07) 03/22/22: The previous comment had not been adequately addressed. The TRANE rooftop unit, which appears to be a new one, has not been updated on the schedule to include the IEER. ************************************************************************************02/16/22 - On the rooftop unit schedule, in addition to the EER listed for the new unit, list the IEER, to comply with Table C403.3.2(1). |
Energy | 03/22/2022 | Rejected | Sheet P600 PLUMBING DETAILS: EN-08) 02/16/22 - Provide ON THE DRAWINGS a schedule of the gas tankless water heater. Include its size, and its minimum required efficiency from Tab;e C404.2. |
Energy | 03/22/2022 | Rejected | EN-09) 03/22/22: Resubmission may result in additional comments. Please number your narrative responses with the identical EN-X number indicated in my comments. This significantly reduces the time required for review of your responses. Per VECC 109.4. If you have questions regarding this energy code review, you can contact me via email at lbaskerville@arlingtonva.us, or call on my mobile number 703-244-0479. The Virginia Energy Conservation Code can be found free online at https://codes.iccsafe.org/content/VECC2018P1 |
Energy | 03/22/2022 | Approved | Sheet P600 PLUMBING DETAILS: EN-08) 02/16/22 - Provide ON THE DRAWINGS a schedule of the gas tankless water heater. Include its size, and its minimum required efficiency from Tab;e C404.2. |
Energy | 03/22/2022 | Rejected | Sheet A001 ZONING AND BUILDING INFO: EN-1) EN-1) 03/22/22 – Current code year cycle is 2018, with the option to use 2015 until June 30, 2022. Your code summary indicates 2012. For Energy Code compliance purposes, you need to state in your code summary section whether you are following VECC or ASHRAE 90.1, and which year. Revise and resubmit. Per VCC section 101.2.*******************************02/16/22: NOT USED. |
Energy | 03/22/2022 | Rejected | Sheet A104 FLOOR PLAN: EN-2) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 - Label the new door with an identification tag, for purposes of addressing the energy criteria associated with new fenestration. |
Energy | 03/22/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: EN-03) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 : New doors and new windows/storefront/curtainwall glazing in the building thermal envelope shall meet the energy code requirements for all three of these metrics: A) the Air Infiltration Rate (whether glazed or opaque), B) the U-factor (whether glazed or opaque) and C) SHGC value (if glazed). Reference Tables C402.1.4, C402.4, C402.5.2. Per Existing Building Code 601.4. State ON THE DRAWINGS the numeric values for your specific fenestration types on the drawings. Citing only the code section numbe |
Energy | 03/22/2022 | Rejected | Sheet E101 RCP: EN-4) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 COMCHECK – The incorrect space type has been entered into comcheck to determine the allowed wattage. You have opted to use the space by space method from Table C405.3.2(2). Each space’s function must be assigned the most closely matched category available. Café seating and dining would be Dining Area, and would be either lounge/bar or fast food, but NOT retail. The Bathroom would fall under Restroom NOT retail, the BOH needs to be separated in to Storage (former vault) and Food Prep Area, but NOT retail. Revise and |
Energy | 03/22/2022 | Rejected | Sheet E101 RCP: EN-5) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 Lighting Controls – Provide the required occupancy sensors per C405.2.1, in the storage room. Revise and resubmit. |
Energy | 03/22/2022 | Rejected | Sheet E101 RCP: EN-6) 03/22/22: The previous comment had not been addressed. Please address the energy code rejection comment. ************************************************************************************02/16/22 Lighting Controls – Provide the required manual controls light reduction for the areas that are NOT in a daylighting zone and that are NOT controlled by an occupancy sensor, per C405.2.2.1 and C405.2.2.2. Revise and resubmit. |
Energy | 03/22/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: EN-07) 03/22/22: The previous comment had not been adequately addressed. The TRANE rooftop unit, which appears to be a new one, has not been updated on the schedule to include the IEER. ************************************************************************************02/16/22 - On the rooftop unit schedule, in addition to the EER listed for the new unit, list the IEER, to comply with Table C403.3.2(1). |
Energy | 03/22/2022 | Rejected | Sheet P600 PLUMBING DETAILS: EN-08) 02/16/22 - Provide ON THE DRAWINGS a schedule of the gas tankless water heater. Include its size, and its minimum required efficiency from Tab;e C404.2. |
Energy | 04/25/2022 | Rejected | EN-09) 04/25/22: Resubmission may result in additional comments. Please number your narrative responses with the identical EN-X number indicated in my comments. This significantly reduces the time required for review of your responses. Per VECC 109.4. If you have questions regarding this energy code review, you can contact me via email at lbaskerville@arlingtonva.us, or call on my mobile number 703-244-0479. The Virginia Energy Conservation Code can be found free online at https://codes.iccsafe.org/content/VECC2018P1 |
Energy | 04/25/2022 | Rejected | Sheet A106 DOOR AND WALL TYPES: EN-10) 4/25/22 - Change the word 'minimum' to 'maximum' U-factor. Per section C402.4.3. |
Energy | 04/25/2022 | Approved | EN-09) 04/25/22: Resubmission may result in additional comments. Please number your narrative responses with the identical EN-X number indicated in my comments. This significantly reduces the time required for review of your responses. Per VECC 109.4. If you have questions regarding this energy code review, you can contact me via email at lbaskerville@arlingtonva.us, or call on my mobile number 703-244-0479. The Virginia Energy Conservation Code can be found free online at https://codes.iccsafe.org/content/VECC2018P1 |
Energy | 04/25/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: EN-10) 4/25/22 - Change the word 'minimum' to 'maximum' U-factor. Per section C402.4.3. |
Energy | 04/25/2022 | Approved | EN-09) 04/25/22: Resubmission may result in additional comments. Please number your narrative responses with the identical EN-X number indicated in my comments. This significantly reduces the time required for review of your responses. Per VECC 109.4. If you have questions regarding this energy code review, you can contact me via email at lbaskerville@arlingtonva.us, or call on my mobile number 703-244-0479. The Virginia Energy Conservation Code can be found free online at https://codes.iccsafe.org/content/VECC2018P1 |
Energy | 04/25/2022 | Approved | Sheet A106 DOOR AND WALL TYPES: EN-10) 4/25/22 - Change the word 'minimum' to 'maximum' U-factor. Per section C402.4.3. |
Energy | 04/26/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: EN-07) 04/25/22 The provided IEER (12.7) does not meet the minimum code required IEER which is 12.8. Revise and resubmit a roof top unit which meets the minimum code efficiency requirements. ************************************************************************************03/22/22: The previous comment had not been adequately addressed. The TRANE rooftop unit, which appears to be a new one, has not been updated on the schedule to include the IEER. ************************************************************************************02/16/22 - On the rooftop unit schedule, in addition to the EER listed for the new unit, list the IEER, to comply with Table C403.3.2(1). |
Energy | 04/26/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: EN-07) 04/25/22 The provided IEER (12.7) does not meet the minimum code required IEER which is 12.8. Revise and resubmit a roof top unit which meets the minimum code efficiency requirements. ************************************************************************************03/22/22: The previous comment had not been adequately addressed. The TRANE rooftop unit, which appears to be a new one, has not been updated on the schedule to include the IEER. ************************************************************************************02/16/22 - On the rooftop unit schedule, in addition to the EER listed for the new unit, list the IEER, to comply with Table C403.3.2(1). |
Energy | 04/26/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: EN-07) 04/25/22 The provided IEER (12.7) does not meet the minimum code required IEER which is 12.8. Revise and resubmit a roof top unit which meets the minimum code efficiency requirements. ************************************************************************************03/22/22: The previous comment had not been adequately addressed. The TRANE rooftop unit, which appears to be a new one, has not been updated on the schedule to include the IEER. ************************************************************************************02/16/22 - On the rooftop unit schedule, in addition to the EER listed for the new unit, list the IEER, to comply with Table C403.3.2(1). |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Is these registers are supply or return registers? |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Please indicate and add note this RTU is existing to remain, and show smoke detector on return duct. |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Show number 3 note next to return duct. |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Please show existing or new exhaust fan on the roof and indicate that is for toilet exhaust. |
Mechanical | 02/09/2022 | Approved | Sheet M103 MECHANICAL DESIGN 3D: Show location of toilet exhaust fan on the roof. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Please coordinate every sheet note with floor plan. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Show location of dryer on floor plan including vent connection. At discharge location show louver with out bird screen. |
Mechanical | 02/09/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: The occupant density #/1000 SF and breathing zone must be 100 and 0.18 for café and bar area (VMC 2018 table 403.3.1.1). |
Mechanical | 02/09/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: Please indicate which RTU is new or existing and show outside air CFM in roof top unit schedule. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Please coordinate location of each toile with architectural plan, and keep each toilet under negative pressure. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Is these registers are supply or return registers? |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Please indicate and add note this RTU is existing to remain, and show smoke detector on return duct. |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Show number 3 note next to return duct. |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Please show existing or new exhaust fan on the roof and indicate that is for toilet exhaust. |
Mechanical | 02/09/2022 | Approved | Sheet M103 MECHANICAL DESIGN 3D: Show location of toilet exhaust fan on the roof. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Please coordinate every sheet note with floor plan. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Show location of dryer on floor plan including vent connection. At discharge location show louver with out bird screen. |
Mechanical | 02/09/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: The occupant density #/1000 SF and breathing zone must be 100 and 0.18 for café and bar area (VMC 2018 table 403.3.1.1). |
Mechanical | 02/09/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: Please indicate which RTU is new or existing and show outside air CFM in roof top unit schedule. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Please coordinate location of each toile with architectural plan, and keep each toilet under negative pressure. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Please coordinate every sheet note with floor plan. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Is these registers are supply or return registers? |
Mechanical | 02/09/2022 | Approved | Sheet M103 MECHANICAL DESIGN 3D: Show location of toilet exhaust fan on the roof. |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Show location of dryer on floor plan including vent connection. At discharge location show louver with out bird screen. |
Mechanical | 02/09/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: Please indicate which RTU is new or existing and show outside air CFM in roof top unit schedule. |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Show number 3 note next to return duct. |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Please indicate and add note this RTU is existing to remain, and show smoke detector on return duct. |
Mechanical | 02/09/2022 | Approved | Sheet M101 MECHANICAL ROOF PLAN: Please show existing or new exhaust fan on the roof and indicate that is for toilet exhaust. |
Mechanical | 02/09/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: The occupant density #/1000 SF and breathing zone must be 100 and 0.18 for café and bar area (VMC 2018 table 403.3.1.1). |
Mechanical | 02/09/2022 | Approved | Sheet M100 MECHANICAL PLAN: Please coordinate location of each toile with architectural plan, and keep each toilet under negative pressure. |
Mechanical | 02/09/2022 | Rejected | Sheet M100 MECHANICAL PLAN: Is these registers are supply or return registers? |
Mechanical | 02/09/2022 | Rejected | Sheet M101 MECHANICAL ROOF PLAN: Please indicate and add note this RTU is existing to remain, and show smoke detector on return duct. |
Mechanical | 02/09/2022 | Rejected | Sheet M101 MECHANICAL ROOF PLAN: Show number 3 note next to return duct. |
Mechanical | 02/09/2022 | Rejected | Sheet M101 MECHANICAL ROOF PLAN: Please show existing or new exhaust fan on the roof and indicate that is for toilet exhaust. |
Mechanical | 02/09/2022 | Rejected | Sheet M103 MECHANICAL DESIGN 3D: Show location of toilet exhaust fan on the roof. |
Mechanical | 02/09/2022 | Rejected | Sheet M100 MECHANICAL PLAN: Please coordinate every sheet note with floor plan. |
Mechanical | 02/09/2022 | Rejected | Sheet M100 MECHANICAL PLAN: Show location of dryer on floor plan including vent connection. At discharge location show louver with out bird screen. |
Mechanical | 02/09/2022 | Rejected | Sheet M100 MECHANICAL PLAN: Is these registers are supply or return registers? |
Mechanical | 02/09/2022 | Rejected | Sheet M101 MECHANICAL ROOF PLAN: Please indicate and add note this RTU is existing to remain, and show smoke detector on return duct. |
Mechanical | 02/09/2022 | Rejected | Sheet M101 MECHANICAL ROOF PLAN: Show number 3 note next to return duct. |
Mechanical | 02/09/2022 | Rejected | Sheet M101 MECHANICAL ROOF PLAN: Please show existing or new exhaust fan on the roof and indicate that is for toilet exhaust. |
Mechanical | 02/09/2022 | Rejected | Sheet M103 MECHANICAL DESIGN 3D: Show location of toilet exhaust fan on the roof. |
Mechanical | 02/09/2022 | Rejected | Sheet M100 MECHANICAL PLAN: Please coordinate every sheet note with floor plan. |
Mechanical | 02/09/2022 | Rejected | Sheet M100 MECHANICAL PLAN: Show location of dryer on floor plan including vent connection. At discharge location show louver with out bird screen. |
Mechanical | 02/09/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: The occupant density #/1000 SF and breathing zone must be 100 and 0.18 for café and bar area (VMC 2018 table 403.3.1.1). |
Mechanical | 02/09/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: Please indicate which RTU is new or existing and show outside air CFM in roof top unit schedule. |
Mechanical | 02/09/2022 | Rejected | Sheet M100 MECHANICAL PLAN: Please coordinate location of each toile with architectural plan, and keep each toilet under negative pressure. |
Mechanical | 02/09/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: The occupant density #/1000 SF and breathing zone must be 100 and 0.18 for café and bar area (VMC 2018 table 403.3.1.1). |
Mechanical | 02/09/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: Please indicate which RTU is new or existing and show outside air CFM in roof top unit schedule. |
Mechanical | 02/09/2022 | Rejected | Sheet M100 MECHANICAL PLAN: Please coordinate location of each toile with architectural plan, and keep each toilet under negative pressure. |
Mechanical | 03/16/2022 | Rejected | Sheet M104 MECHANICAL SCHEDULES: Please provide uncorrected outdoor air intake (Vou) and system ventilation efficiency (Ev) for outside air calculations, and coordinate outside air CFM between rooftop unit schedule and outside air calculations (VMC 2015 or 2018 chapter 4).. |
Mechanical | 03/16/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: Please provide uncorrected outdoor air intake (Vou) and system ventilation efficiency (Ev) for outside air calculations, and coordinate outside air CFM between rooftop unit schedule and outside air calculations (VMC 2015 or 2018 chapter 4).. |
Mechanical | 03/16/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: Please provide uncorrected outdoor air intake (Vou) and system ventilation efficiency (Ev) for outside air calculations, and coordinate outside air CFM between rooftop unit schedule and outside air calculations (VMC 2015 or 2018 chapter 4).. |
Mechanical | 03/16/2022 | Approved | Sheet M104 MECHANICAL SCHEDULES: Please provide uncorrected outdoor air intake (Vou) and system ventilation efficiency (Ev) for outside air calculations, and coordinate outside air CFM between rooftop unit schedule and outside air calculations (VMC 2015 or 2018 chapter 4).. |
Plumbing | 02/14/2022 | Rejected | 2-14-22 Pg P600 Tee fitting required at Trap arm connection. 2018 VPC 706.3 |
Plumbing | 02/14/2022 | Rejected | 2/14/22 Pg P300 Plans seem to indicate Waste disposer connection. Waste Disposer prohibited to connect/drain to GI . 2018 VPC 1003.3.2 |
Plumbing | 02/14/2022 | Approved | 2-14-22 Pg P600 Tee fitting required at Trap arm connection. 2018 VPC 706.3 |
Plumbing | 02/14/2022 | Approved | 2/14/22 Pg P300 Plans seem to indicate Waste disposer connection. Waste Disposer prohibited to connect/drain to GI . 2018 VPC 1003.3.2 |
Plumbing | 02/14/2022 | Rejected | 2-14-22 Pg P600 Tee fitting required at Trap arm connection. 2018 VPC 706.3 |
Plumbing | 02/14/2022 | Rejected | 2/14/22 Pg P300 Plans seem to indicate Waste disposer connection. Waste Disposer prohibited to connect/drain to GI . 2018 VPC 1003.3.2 |
Plumbing | 02/14/2022 | Rejected | 2-14-22 Please provide location and additional information on Grease Interceptor. Size , calculation, location and details |
Plumbing | 02/14/2022 | Approved | 2-14-22 Pg P600 Tee fitting required at Trap arm connection. 2018 VPC 706.3 |
Plumbing | 02/14/2022 | Approved | 2/14/22 Pg P300 Plans seem to indicate Waste disposer connection. Waste Disposer prohibited to connect/drain to GI . 2018 VPC 1003.3.2 |
Plumbing | 02/14/2022 | Rejected | 2-14-22 Pg P600 Tee fitting required at Trap arm connection. 2018 VPC 706.3 |
Plumbing | 02/14/2022 | Rejected | 2/14/22 Pg P300 Plans seem to indicate Waste disposer connection. Waste Disposer prohibited to connect/drain to GI . 2018 VPC 1003.3.2 |
Plumbing | 03/21/2022 | Rejected | 2-14-22 Please provide location and additional information on Grease Interceptor. Size , calculation, location and details
3-21-22 Please be advised requirements for Grease Interceptors is required under the 2018 VPC 1003.3.1 . A Code Modification will be required to be submitted and reviewed thru the Building Official. If u may have any further questions please contact me 703 228-3873 |
Plumbing | 03/21/2022 | Rejected | 3-21-22 Pg A000 states 2012 code year please update. Application states 2018 code year |
Plumbing | 03/21/2022 | Rejected | 3-21-22 Pg A000 states 2012 code year please update. Application states 2018 code year |
Plumbing | 03/21/2022 | Approved | 3-21-22 Pg A000 states 2012 code year please update. Application states 2018 code year |
Plumbing | 03/21/2022 | Approved | 3-21-22 Pg A000 states 2012 code year please update. Application states 2018 code year |
Plumbing | 04/22/2022 | Approved | 2-14-22 Please provide location and additional information on Grease Interceptor. Size , calculation, location and details
3-21-22 Please be advised requirements for Grease Interceptors is required under the 2018 VPC 1003.3.1 . A Code Modification will be required to be submitted and reviewed thru the Building Official. If u may have any further questions please contact me 703 228-3873
4-22-22 Respectfully please be advised Per Mr Dodge . The FOG policy has been updated to include Coffee Shops. Respectfully please contact Mr Dodge if you require further clarification. At this time a Grease interceptor is required. Please provide information as stated from my 2-14-22 comment. |
Plumbing | 04/22/2022 | Rejected | 2-14-22 Please provide location and additional information on Grease Interceptor. Size , calculation, location and details
3-21-22 Please be advised requirements for Grease Interceptors is required under the 2018 VPC 1003.3.1 . A Code Modification will be required to be submitted and reviewed thru the Building Official. If u may have any further questions please contact me 703 228-3873
4-22-22 Respectfully please be advised Per Mr Dodge . The FOG policy has been updated to include Coffee Shops. Respectfully please contact Mr Dodge if you require further clarification. At this time a Grease interceptor is required. Please provide information as stated from my 2-14-22 comment. |
Plumbing | 04/22/2022 | Approved | 2-14-22 Please provide location and additional information on Grease Interceptor. Size , calculation, location and details
3-21-22 Please be advised requirements for Grease Interceptors is required under the 2018 VPC 1003.3.1 . A Code Modification will be required to be submitted and reviewed thru the Building Official. If u may have any further questions please contact me 703 228-3873
4-22-22 Respectfully please be advised Per Mr Dodge . The FOG policy has been updated to include Coffee Shops. Respectfully please contact Mr Dodge if you require further clarification. At this time a Grease interceptor is required. Please provide information as stated from my 2-14-22 comment. |
Public Health Division | 02/15/2022 | Rejected | Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf |
Public Health Division | 02/15/2022 | Rejected | Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked. |
Public Health Division | 02/15/2022 | Rejected | Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage.
https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
|
Public Health Division | 02/15/2022 | Rejected | Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf |
Public Health Division | 02/15/2022 | Rejected | Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked. |
Public Health Division | 02/15/2022 | Rejected | Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage.
https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
|
Public Health Division | 02/15/2022 | Approved | Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf |
Public Health Division | 02/15/2022 | Approved | Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked. |
Public Health Division | 02/15/2022 | Approved | Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage.
https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
|
Public Health Division | 02/15/2022 | Approved | Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf |
Public Health Division | 02/15/2022 | Approved | Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked. |
Public Health Division | 02/15/2022 | Approved | Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage.
https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
|
Public Health Division | 02/15/2022 | Approved | Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation. See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf |
Public Health Division | 02/15/2022 | Approved | Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked. |
Public Health Division | 02/15/2022 | Approved | Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage.
https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
|
Public Health Division | 03/16/2022 | Rejected | Confirm all foods supplies are from an approved source. |
Public Health Division | 04/21/2022 | Approved | Confirm all foods supplies are from an approved source. |
Public Health Division | 04/21/2022 | Approved | Confirm all foods supplies are from an approved source. |
Public Health Division | 04/21/2022 | Approved | Confirm all foods supplies are from an approved source. |
Structural | 03/23/2022 | Approved | Only one structural sheet was submitted for review. Are there more sheets? |
Structural | 03/23/2022 | Approved | Please submit structural sheet with building code year, live loads, etc |
Structural | 03/23/2022 | Approved | On sheet S231, how tall is the retaining wall? |
Structural | 03/23/2022 | Approved | Please provide the safety factor for sliding and overturning of the retaining wall |
Structural | 03/23/2022 | Approved | Only one structural sheet was submitted for review. Are there more sheets? |
Structural | 03/23/2022 | Approved | Please submit structural sheet with building code year, live loads, etc |
Structural | 03/23/2022 | Approved | On sheet S231, how tall is the retaining wall? |
Structural | 03/23/2022 | Approved | Please provide the safety factor for sliding and overturning of the retaining wall |
Structural | 03/23/2022 | Approved | Only one structural sheet was submitted for review. Are there more sheets? |
Structural | 03/23/2022 | Approved | Please submit structural sheet with building code year, live loads, etc |
Structural | 03/23/2022 | Approved | On sheet S231, how tall is the retaining wall? |
Structural | 03/23/2022 | Approved | Please provide the safety factor for sliding and overturning of the retaining wall |
Structural | 03/23/2022 | Rejected | Only one structural sheet was submitted for review. Are there more sheets? |
Structural | 03/23/2022 | Rejected | Please submit structural sheet with building code year, live loads, etc |
Structural | 03/23/2022 | Rejected | On sheet S231, how tall is the retaining wall? |
Structural | 03/23/2022 | Rejected | Please provide the safety factor for sliding and overturning of the retaining wall |
Zoning | 02/15/2022 | Rejected | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Rejected:
1. please provide existing and proposed parking plan and count for the site.
2. On the parking plan, please show the various dimensions of the parking spaces and driveway
3. For parking requirements, please refer to section 14.3.7A and 14.3.3C for parking dimensions
4. Please provide a zoning comment response letter when resubmitting revisions.
Reviewer:
Mudoh Mbah SAM
Tel: 703-228-3727
Email: mmbah@arlingtonva.us |
Zoning | 03/22/2022 | Rejected | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Rejected:
1. please provide existing and proposed parking plan and count for the site.
2. On the parking plan, please show the various dimensions of the parking spaces and driveway
3. For parking requirements, please refer to section 14.3.7A and 14.3.3C for parking dimensions
4. Please provide a zoning comment response letter when resubmitting revisions.
Reviewer:
Mudoh Mbah SAM
Tel: 703-228-3727
Email: mmbah@arlingtonva.us |
Zoning | 03/22/2022 | Rejected | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Rejected:
1. please provide existing and proposed parking plan and count for the site.
2. On the parking plan, please show the various dimensions of the parking spaces and driveway
3. For parking requirements, please refer to section 14.3.7A and 14.3.3C for parking dimensions
4. Please provide a zoning comment response letter when resubmitting revisions.
Reviewer:
Mudoh Mbah SAM
Tel: 703-228-3727
Email: mmbah@arlingtonva.us |
Zoning | 03/22/2022 | Rejected | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Total parkin provided = 15
Rejected:
1. It appears the restaurant proposes a drive-through window. This is not clear in your use description. Per $$7.1.3 use table, a use permit is required for a drive-through-window for this zoning district. Staff did not find any use permit approval for the drive through window. Please clarify or visit the county website for a use permit application.
2. The 215in (17.9ft) depth dimension provided for parking does not comply. A minimum of 18ft depth is required. Please reck your measurement.
3. Show the dimension |
Zoning | 03/22/2022 | Approved | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Rejected:
1. please provide existing and proposed parking plan and count for the site.
2. On the parking plan, please show the various dimensions of the parking spaces and driveway
3. For parking requirements, please refer to section 14.3.7A and 14.3.3C for parking dimensions
4. Please provide a zoning comment response letter when resubmitting revisions.
Reviewer:
Mudoh Mbah SAM
Tel: 703-228-3727
Email: mmbah@arlingtonva.us |
Zoning | 03/22/2022 | Approved | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Rejected:
1. please provide existing and proposed parking plan and count for the site.
2. On the parking plan, please show the various dimensions of the parking spaces and driveway
3. For parking requirements, please refer to section 14.3.7A and 14.3.3C for parking dimensions
4. Please provide a zoning comment response letter when resubmitting revisions.
Reviewer:
Mudoh Mbah SAM
Tel: 703-228-3727
Email: mmbah@arlingtonva.us |
Zoning | 04/19/2022 | Approved | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Total parkin provided = 15 (conforming)
Rejected:
1. It appears the restaurant proposes a drive-through window. This is not clear in your use description. Per $$7.1.3 use table, a use permit is required for a drive-through-window for this zoning district. Staff did not find any use permit approval for the drive through window. Please clarify or visit the county website for a use permit application.
2. The 215in (17.9ft) depth dimension provided for parking does not comply. A minimum of 18ft depth is required. Please reck your measurement.
3. Show |
Zoning | 04/19/2022 | Approved | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Total parkin provided = 15 (conforming)
Rejected:
1. It appears the restaurant proposes a drive-through window. This is not clear in your use description. Per $$7.1.3 use table, a use permit is required for a drive-through-window for this zoning district. Staff did not find any use permit approval for the drive through window. Please clarify or visit the county website for a use permit application.
2. The 215in (17.9ft) depth dimension provided for parking does not comply. A minimum of 18ft depth is required. Please reck your measurement.
3. Show |
Zoning | 04/19/2022 | Rejected | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed.
Total parkin provided = 15 (conforming)
Rejected:
1. It appears the restaurant proposes a drive-through window. This is not clear in your use description. Per $$7.1.3 use table, a use permit is required for a drive-through-window for this zoning district. Staff did not find any use permit approval for the drive through window. Please clarify or visit the county website for a use permit application.
2. The 215in (17.9ft) depth dimension provided for parking does not comply. A minimum of 18ft depth is required. Please reck your measurement.
3. Show |
Zoning | 05/02/2022 | Rejected | Rejected:
1. As discussed, Please revise the enclosure around the trash bin to be maximum 4ft in height as required.
$$3.2.6A.3e: ) The front, side and rear yard requirements of this zoning ordinance shall not be
deemed to prohibit any otherwise lawful fence or wall which is not more than four
feet high; provided, however, that a fence or wall along the rear lot line or along a
side lot line to the rear of the required setback line may be erected to a height not
exceeding seven feet; provided, further, that in side and rear yards of corner lots,
fences up to six feet in height may be erected in the required setback in order to
permit the enclosure of the side and rear yards for privacy so long as the
requirements of §3.2.6.A.4, rel |
Zoning | 05/02/2022 | Approved | Rejected:
1. As discussed, Please revise the enclosure around the trash bin to be maximum 4ft in height as required.
$$3.2.6A.3e: ) The front, side and rear yard requirements of this zoning ordinance shall not be
deemed to prohibit any otherwise lawful fence or wall which is not more than four
feet high; provided, however, that a fence or wall along the rear lot line or along a
side lot line to the rear of the required setback line may be erected to a height not
exceeding seven feet; provided, further, that in side and rear yards of corner lots,
fences up to six feet in height may be erected in the required setback in order to
permit the enclosure of the side and rear yards for privacy so long as the
requirements of §3.2.6.A.4, rel |
Zoning | 05/02/2022 | Approved | Rejected:
1. As discussed, Please revise the enclosure around the trash bin to be maximum 4ft in height as required.
$$3.2.6A.3e: ) The front, side and rear yard requirements of this zoning ordinance shall not be
deemed to prohibit any otherwise lawful fence or wall which is not more than four
feet high; provided, however, that a fence or wall along the rear lot line or along a
side lot line to the rear of the required setback line may be erected to a height not
exceeding seven feet; provided, further, that in side and rear yards of corner lots,
fences up to six feet in height may be erected in the required setback in order to
permit the enclosure of the side and rear yards for privacy so long as the
requirements of §3.2.6.A.4, rel |
Zoning | 05/16/2022 | Approved | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed. Total parking provided = 15 (conforming). Enclosure around dumpster is max. 4ft height as required.
APPROVAL NOTE:
1. Work must be done as shown on the plan and plat submitted for zoning review on 9/22/2017. Any alteration to the above will need zoning review and approval.
Reviewer:
Mudoh Mbah
Tel: 703-228-3727
Email: mmbah@arlingtonva.us
|
Zoning | 05/16/2022 | Approved | Interior and exterior alteration including parking of an existing building in C-2 district. Proposed use is restaurant (coffee cafe). Proposed seating capacity is 50. Proposed use is allowed. Total parking provided = 15 (conforming). Enclosure around dumpster is max. 4ft height as required.
APPROVAL NOTE:
1. Work must be done as shown on the plan and plat submitted for zoning review on 9/22/2017. Any alteration to the above will need zoning review and approval.
Reviewer:
Mudoh Mbah
Tel: 703-228-3727
Email: mmbah@arlingtonva.us
|