Review | Review Date | Status | Comments |
Bike Review | 06/28/2022 | Rejected | Sheet A2-10 - FLOOR PLAN -LEVEL 01 (STREET LEVEL): Since design of the Class 1 bike facilities is part of the Footing to Grade permit, add sheet A3.51 ENLARGED PLAN LOADING DOCK & PARKING RAMP as part of this permit review to show the ground floor bike storage room details. |
Bike Review | 06/28/2022 | Rejected | Sheet A2-01 - FLOOR PLAN -LEVEL G2: Since design of the Class 1 bike facilities is part of the Footing to Grade permit, add sheet A3-54 ENLARGED PLANS BIKE STORAGE as part of this permit review to show the details for the G2 and G1 bike storage rooms. |
Building | 07/01/2022 | Rejected | Rejected - Please see Levels G2, G1 and Street level comments on Permit CNEW-49805/B2200722. Please address those plan review comments and coordinate with this Permit Set prior to resubmitting. |
DES/RE Vacation - Encroachment | 06/06/2022 | Rejected | Conditions of vacations/encroachments haven't been met. |
Electrical | 06/30/2022 | Rejected | The 'scope' of work indicates: "NEW CONSTRUCTION OF A TWO LEVEL UNDERGROUND PARKING GARAGE LEVELS G1 AND G2". There appears to be a 'compete' set of plans for the entire building in this plan set. Please submit the electrical sheets that 'only' correspond with the 'scope' of work. |
Electrical | 06/30/2022 | Rejected | Provide the grounding electrode conductor wire size for the 'Metal Underground Water Pipe'. Refer to the 'MAIN GROUNDING ELECTRODE SYSTEM' detail shown on sheet E5.00. NEC Table 250.66. Section 109.3 of the Virginia Construction Code. |
Electrical | 06/30/2022 | Rejected | Provide the size of the grounding electrode conductor for the 'Fire Pump' service. Refer to the 'MAIN GROUNDING ELECTRODE SYSTEM' detail shown on sheet E5.00 and riser diagram shown on sheet E5.01. NEC Table 250.66. Section 109.3 of the Virginia Construction Code. |
Electrical | 06/30/2022 | Rejected | Additional comments may be forthcoming. |
Electrical | 06/30/2022 | Rejected | The 'scope' of work indicates: "NEW CONSTRUCTION OF A TWO LEVEL UNDERGROUND PARKING GARAGE LEVELS G1 AND G2". There appears to be a 'compete' set of plans for the entire building in this plan set. Please submit the electrical sheets that 'only' correspond with the 'scope' of work. |
Electrical | 06/30/2022 | Rejected | Provide the grounding electrode conductor wire size for the 'Metal Underground Water Pipe'. Refer to the 'MAIN GROUNDING ELECTRODE SYSTEM' detail shown on sheet E5.00. NEC Table 250.66. Section 109.3 of the Virginia Construction Code. |
Electrical | 06/30/2022 | Rejected | Provide the size of the grounding electrode conductor for the 'Fire Pump' service. Refer to the 'MAIN GROUNDING ELECTRODE SYSTEM' detail shown on sheet E5.00 and riser diagram shown on sheet E5.01. NEC Table 250.66. Section 109.3 of the Virginia Construction Code. |
Electrical | 06/30/2022 | Rejected | Additional comments may be forthcoming. |
Electrical | 07/29/2022 | Rejected | The 'One Line Electrical Riser Diagram' shows a 400 ampere service disconnect switch (Retail Service Disconnect). The service entrance conductors (750KCMIL AL), are shown to be supplied directly from the 'Utility 480V XFMR'. The length of the 'unfused' service entrance conductors 'must' comply with the requirements of NEC Article 230.70 (A)(1). Currently, these conductors are shown to be 'over head' and not installed in a minimum of 2" concrete as permitted by NEC Article 230.6. Refer to sheets E4.01 and E5.01. Please clarify. Section 109.3 of the Virginia Construction Code. |
Energy | 06/15/2022 | Approved | Sheet .G0-00 - COVER SHEET: EN-1) 06/15/22 APPROVED AS NOTED: Add this note to the cover sheet: “The energy code compliance of the spaces and equipment within the scope of this footing to grade permit and construction, shall be met in accordance with the tower permit # B2200722 energy code criteria. No build-out of these spaces or equipment installation within the footing to grade construction scope, shall occur until the tower permit has energy code approval. The energy code compliance of the envelope and equipment within the footing to grade permit shall be revised, and resubmitted, to comply with the approved tower permit envelope and equipment energy code compliance.” |
Environmental Services | 06/29/2022 | Rejected | Please confirm plumbing fixture count and clarify if a water meter will be requested for the garage separate from the building. |
Fire Prevention | 06/17/2022 | Approved | See above ground submittal for all fire protection system issue or comments. Approved. |
Garage/Parking Review | 06/30/2022 | Rejected | Sheet A2-02 - FLOOR PLAN -LEVEL G1: Provide queue analysis at the garage entrances demonstrating that no vehicles are queuing within the public right of way. See https://topics.arlingtonva.us/building/parking-management-plan/ for more information on the requirements, guidelines and examples for the Queue Analysis |
Garage/Parking Review | 06/30/2022 | Rejected | Sheet A2-02 - FLOOR PLAN -LEVEL G1: Please provide dimensions of the parking spaces. |
Structural | 06/30/2022 | Rejected | Please submit SIER resumes and certifications
|
Structural | 06/30/2022 | Rejected | Please submit a separate permit for the sheeting and shoring. |
Structural | 06/30/2022 | Rejected | Please schedule a preconstruction meeting be sending an email to vortega@arlingtonva.us. |
Structural | 06/30/2022 | Rejected | Due to the project’s scope of work, Special Inspections will be required. Please submit the Statement of Special Inspections (SSI) packet. This statement is to be prepared by the Structural Engineer of Record (SER), and is used for identifying the structural items that require special inspection.
(1) The SSI shall cover the special inspection requirements for the completion of the project.
(2) All fields on the SSI must be completed. For irrelevant items, please mark N/A. All relevant items must be marked with the SIER/SER initials. For items not specified in the Statement, please write in the inspection in the field marked “other inspection” on page 59.
(3) The SSI shall be signed by the Structural Engineer of Record (SER), the Spec |
Zoning | 06/28/2022 | Rejected | The proposed 21 compact spaces represent a 28% ratio of compact spaces. On the County Board report it was approved a 26%, which represent 19 compact spaces. This proposed increase could represent that a site plan amendment will be required to allow this increase on the number of compact parking spaces. |
Zoning | 06/28/2022 | Rejected | On sheets A2-01 & A2-02 the number of standard parking spaces and EV spaces on the tabulation is different than the ones shown on the drawings. Also, the sum is incorrect. |
Zoning | 06/28/2022 | Rejected | Provide details that the area of the alley that connects Wilson Blvd. and Clarendon Blvd. it is designed in order to resist the weight of an emergency vehicle. |
Zoning | 06/28/2022 | Rejected | Add the following Zoning standard note on sheets M-101, M-102, P-101 and P-102:
“All mechanical, electrical and plumbing work, including but not limited to, ductwork, piping, fans, equipment, switches and sensors shall be installed so as not to encroach into required dimensions of parking spaces including height, width, stale and drive aisle. A minimum height clearance of 98 inches for handicap van and vanpool spaces and 84 inches for all other spaces must be maintained at all-time including the drive aisles and garage entrances used to navigate to those spaces.” |