Review | Review Date | Status | Comments |
Building | 06/14/2022 | Rejected | NOTE. Outside dining requires a separate CO. No response required. You can show the outside dining occupant load in your bathroom fixture calculations with a note that you will file for a separate CO. |
Building | 06/14/2022 | Rejected | Please show EXIT signs on plan. |
Building | 06/22/2022 | Rejected | Sheet A-101.00 Construction Plan: Private dining room 0005 must be provided with a swinging door for egress. See VCC 1010.1.2. |
Building | 06/22/2022 | Rejected | Sheet A-101.00 Construction Plan: Box 1 on the Accessibility Compliance Form is checked. 5 % of both men's and women's toilets/ toilet compartments are required to accessible. The new accessible ADA toilet room only provides for one men's or women's, therefore one of the existing toilets would have to be accessible. The current layout of the existing toilet rooms does not appear to provide the required toe space at compartments with walls to the floor, compartment door maneuvering clearances and/or doors in series. You may want to look at VEBC 404.4.10 or use the new ADA toilet room as one of the men's or women's and change the ADA form to box 4 and show a path for compliance as upgrades. Bear in mind the new toilet room is required to be a |
Electrical | 06/15/2022 | Rejected | Provide a load calculation , Provide a demand load on all panels. |
Electrical | 06/15/2022 | Rejected | Provide Exit signs. |
Mechanical | 06/17/2022 | Rejected | Sheet M-001 Mech Notes: Drawing number for roof mechanical plan should be M-102. please coordinate with submitted plans. |
Mechanical | 06/17/2022 | Rejected | Sheet M-403 Kitchen Equip: Please coordinate total exhaust CFM between M-403 and M-401 Captive drawings. |
Mechanical | 06/17/2022 | Rejected | Sheet M-102 Roof Mech Plan: Please indicate the area serves by XRTU-1 and show associated supply and return duct on floor plan M-101. |
Mechanical | 06/17/2022 | Rejected | Sheet M-101 1st Floor Mech Plan: Please indicate type of water heater, if gas, show vent and combustion air and discharge location. |
Mechanical | 06/17/2022 | Rejected | Sheet M-102 Roof Mech Plan: Drawing number for roof mechanical plan should be M-102. please coordinate with submitted plans. |
Mechanical | 06/17/2022 | Rejected | Sheet M-701 Mech Sched: Please provide outside air calculations for each area for correct number of people and EZ of 0.8 (VMC 2018 table 403.3.1.1). |
Plumbing | 06/29/2022 | Rejected | A Waste Water Survey Form is required. Please use the link provided. https://www.arlingtonva.us/files/sharedassets/public/water/documents/arlington_iu_survey_2021_211108.pdf And forward it to Wilson Dodge the pretreatment coordinator at wrdodge@arlingtonva.us |
Plumbing | 06/29/2022 | Rejected | 6-28-22 Please provide complete GI calculations for all GI's, to include any additional fixtures added to GI. 2018 VPC 1003.3.3.5.1 |
Plumbing | 06/29/2022 | Rejected | 6-28-22 Please provide complete Gas riser diagram. Please include piping material, total length, total BTU |
Public Health Division | 06/15/2022 | Rejected | Confirm there will be a certified food protection manager provided at the pre-opening inspection and at all hours of operation.
See the list of approved providers; https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/08/Certified-Food-Manager-Guidelines_2021.08.02.pdf |
Public Health Division | 06/15/2022 | Rejected | Provide the proposed menu. The menu should include a consumer advisory disclosure and reminder for animal-derived foods offered raw or undercooked. |
Public Health Division | 06/15/2022 | Rejected | Complete and upload the Application for Foodservice Plan Review found on the Arlington County webpage.
https://health.arlingtonva.us/wp-content/uploads/sites/25/2021/09/PHD-Food-Service-Plan-Review-Application_Fillable_2021.09.01.pdf
|
Public Health Division | 06/15/2022 | Rejected | Provide the food service equipment layout, with all food service identified in the equipment schedule. |
Zoning | 06/28/2022 | Rejected | The outdoor seating will not be approved as part of this building permit. The applicant will need to apply for a Certificate of Occupancy for the outdoor seating at contactzoning@arlingtonva.us. All outdoor seating on this permit will need to be covered with a revision cloud and labeled as for reference only or completely removed. |
Zoning | 06/29/2022 | Rejected | The outdoor seating will not be approved as part of this building permit. The applicant will need to apply for a Certificate of Occupancy for the outdoor seating at contactzoning@arlingtonva.us. The outdoor seating could be obtained after the applicant obtain the indoor seating certificate of occupancy. All outdoor seating on this permit will need to be covered with a revision cloud and labeled as for reference only or completely removed. |