Review | Energy |
Review Date | 06/15/2022 |
Status | Approved |
Comments |
Sheet .G0-00 - COVER SHEET: EN-1) 06/15/22 APPROVED AS NOTED: Add this note to the cover sheet: “The energy code compliance of the spaces and equipment within the scope of this footing to grade permit and construction, shall be met in accordance with the tower permit # B2200722 energy code criteria. No build-out of these spaces or equipment installation within the footing to grade construction scope, shall occur until the tower permit has energy code approval. The energy code compliance of the envelope and equipment within the footing to grade permit shall be revised, and resubmitted, to comply with the approved tower permit envelope and equipment energy code compliance.” |
|