Review   Review       Date Status   Comments   
Building05/30/2019Approved Sheet A-701 WINDOW AND DOOR SCHEDULES and DETAILS: Any Exit doors serving an assembly use with more than 49 occupants must comply with Section 1008.1.10 and be equipped with panic hardware (if door has a lath and/or lock).
Building05/03/2019Approved Sheet A-016 PATIO DETAIL PLAN AND ELEVATIONS: Sheet A-016: Note 4 mentions Civil Drawings; Do you have sheets under Civil Plans set?
Building05/03/2019Approved Sheet S-100 FRAMING PLAN SECTIONS AND DETAILS: Sheet S-100: Please describe the method of attachment for the the canopy to the exterior wall (top and bottom).
Building05/03/2019Approved Sheet AI-301 RESTROOM PLAN and ELEVATIONS: Sheet AI-301: You must show (on these drawings) Compliance with the following code sections for accessibility: Section 604.5.1: FIXED SIDE WALL GRAB BARS (A117.1-2009) Section 604.7; DISPENSERS Section 606.3 HEIGHT (of lavatories)
Building05/03/2019Approved Sheet E-003 ENERGY CODE CALCULATIONS: Sheet E-003: NO CONTENT?
Building05/03/2019Approved Sheet A-701 WINDOW AND DOOR SCHEDULES and DETAILS: Tempered glazing in Hazardous Locations are described in Section 2406.4/VCC 2012 must be labeled in accordance with Section 2406.3/VCC 2012.
Building05/03/2019Approved Sheet A-013 ARCHITECTURAL SITE DETAILS: Architectural Site Details: Provide detailed structural drawings for all concrete footings shown.
Building05/03/2019Approved Sheet A-101 BUILDING FLOOR PLAN: According to Section 2902.2 of the VCC 2012 Separate facilities are required for an occupant load exceeding 15. Therefore, please label each restroom according to gender.
Building05/02/2019Approved Sheet A-004 ACCESSIBILITY STANDARDS: Sheet A-004: On the interior view showing the accessible restroom toilet seat and grab bars. Show the toilet paper dispenser location in accordance with Section and Figure 604.7 of the A117.1-2009 (18" minimum from floor; 42" maximum from rear wall for surface mounted toilet paper dispenser.
Building05/02/2019Approved Sheet A-004 ACCESSIBILITY STANDARDS: Sheet A-004: On the interior view showing the accessible restroom toilet seat and grab bars. You need to show the min. and max. height of the toilet seat measured form the rim of the seat. nit including the seat drop cover. (Figure 604.4/A117.1-2009).
DES:Engineering05/13/2019Approved PULL & REPLACE LAVS & WC'S. REMOVING DF, INSTALLING 4 SINKS (3-HAND, 1 MOP) & 3-COMP SINK. 11.5 NEW DFUS COUNTED
DES:Water/Sewer Engineering07/09/2019Approved NO NEW DFU'S
Energy 06/07/2019Approved EN-6) comment dated 6-7-19: The previous comment has not been addressed. Per our prior discussion, the central areas between the two doors may be considered as one daylighting zone, rather than 2 separate DZs with a couple lights requiring general lighting control sandwiched between the zones. Or you may choose to have 2 separate zones that abut each other so there is not a couple of track  more...
Energy 06/06/2019Approved Sheet P-701 PLUMBING ISOMETRICS: EN-11 - Energy Plan Review Note - APPROVED AS NOTED - 6/6/19: Water heater shall meet or exceed the minimum efficiency requirement of Table C404.2 of the 2012 VECC. For the gas water heater listed in the schedule, the minimum efficiency is 80% thermal efficiency.
Energy 06/06/2019Approved Sheet A-701 WINDOW AND DOOR SCHEDULES and DETAILS: EN-12 Energy Plan Reviewer note - APPROVED AS NOTED - Table C402.4.3 added to the drawing for reference for the energy inspector.
Energy 05/13/2019Approved EN-1) comment dated 5-13-19: Sheet A202, Note 8 - State in note 8, for the new infill wall areas, that new insulation to match the existing insulation's location and R-value shall be provided, per Virginia Rehab Code (VRC) section 403.1 General - Alterations shall be such that the existing building or structure is no less conforming to the provisions of the International Building Code than the  more...
Energy 05/13/2019Approved EN-3) comment dated 5-13-19: Sheet A701 Window and Door Schedule - state on the drawing the air infiltration rates for all new windows and doors in the building thermal envelope, to comply with TABLE C402.4.3 MAXIMUM AIR INFILTRATION RATE FOR FENESTRATION ASSEMBLIES
Energy 05/13/2019Approved EN-4) comment dated 5-13-19: Sheet A701 Window and Door Schedule - state on the drawing the U-factor and the SHGC for the DT storefront, to comply with section C402.3.3 Maximum U-factor and SHGC. It is not clear from the way the U-factor and SHGC are written for the storefront doors whether it also applies to the windows or not.
Energy 05/13/2019Approved EN-5) comment dated 5-13-19: Sheet E401 Lighting Plan - clarify how the 2 workrooms meet the requirements for occupancy sesnors in section C405.2.2.2 Occupancy sensors. State on the drawings the max time before the occupancy sensors turn off, and state whether the occupancy sensors are manual on, or automatic on, and whether they are on to 100% power or 50% power.
Energy 05/13/2019Approved EN-2) comment dated 5-13-19: Sheet A202, Note 8 - State in note 8, for the new infill wall areas, that new air barrier shall be provided to be made continuous with existing air barrier, per Virginia Rehab Code (VRC) section 403.1 General - Alterations shall be such that the existing building or structure is no less conforming to the provisions of the International Building Code than the existing  more...